WE Report

Audits



Rig Intake

No person selected

Report No.

7957
Rig Intake Risk Assessment

Type of audit

Rig Intake
Rig Intake

Auditee/Customer

Rig Intake
OKEA/SVAL

Date

2025/01/22

319 days ago

Findings

20
Number of findings

Status

In process
Rig Intake


Rig Intake Risk Assessment
Summary

OKEA ASA (OKEA) and SVAL Energy AS (SVAL) has completed the rig selection process and have established an agreement with Odfjell Drilling (Odfjell) to utilise the rig Deepsea Yantai (DSY). OKEA and Sval have made an agreement to carry out a joint rig intake for Deepsea Yantai. OKEA is planning to drill two production wells on Bestla and Sval will Plug & permanent Abandon the Vale well. OKEA will be the first operator with a commencement window for the DSY between July 1st, 2025, and December 31st, 2025. Well Expertise (WE) has been contracted to lead the rig intake process on behalf of OKEA and Sval.
A Rig Intake Risk Assessment was carried out on Teams 16.01.2025.
The participants identified totally 33 risks, however only 10 risks are medium after compensating measures and will have special focus in the rig intake process. The medium risks will be included in the rig intake plan. No residual risks were classified as red.
17 actions were identified and discussed and followed up in this report.

Findings

  • Actions

    Open

    Open
    Deadline was:

    A-1a: OKEA IT Erwin Geis Establish contract with Speedcast with back-up solution for OKEA operations
    A-1b: WE Lars Solvang Establish contract with Speedcast through Odfjell with back-up solution

    1A:OKEA IT contract established with Options AS for both Starlink communications and IT. Action closed for OKEA
    1B:Pending action Lars Solvang to establish agreement for Sval PP&A scope with earliest commencement 1.1.25 – Due date extended to meet Sval commencement date.

  • Actions

    Open

    Open
    Deadline was:

    A-2a: OKEA IT Erwin Geis to ensure back-up solution to Speedcast (VSAT or equivalent) for OKEA operations
    A-2b: WE Lars Solvang to ensure back-up solution to Speedcast (VSAT or equivalent) for Sval operations

    2A:OKEA IT contract established with Options AS for both Starlink communications and IT. Back-up solution LTE agreed and included in the contract. Action closed for OKEA
    2B:Pending action Lars Solvang to establish agreement for Sval PP&A scope with earliest commencement 1.1.25 – Due date extended to meet Sval commencement date.

  • Actions

    Open

    Open
    Deadline was:

    A-3a:OKEA Logistics and base manager Morten Veiset to ensure that Inspection services are incorporated incorporated in logistics base contract scope of work for OKEA operations
    A-3b:WE Logistics Johan Kjos to ensure that Inspection services are incorporated incorporated in logistics base contract scope of work for Sval operations

    3A – Confirmed included in OKEA base contract – OKEA action closed
    3B – Pending due date extended to meet Sval commencement date

  • Actions

    Open

    Open
    Deadline was:

    Roel/Johan: A-4:L3-MODU-ALL-TO-PR-016 Temporary Equipment to be sent out to service companies.
    Karina/Morten: Ensure third party equipment is according to working environment requirements.
    Roger/DSV: Ensure that equipment is included in the rigs maintenance system

  • Actions

    Closed


    Closed


    Deadline was:

    A-5: Make sure that routines are in place for Cement unit handover between wells – review handover documentation (Baker cement unit) and verify cement unit maintenance system towards SLB

    Maintenenace review scheduled for Apil 2nd. Handover meeting confirmed by SLB.
    Maintenance review identified several observation. Action closed here and follow-up in ARV report 8537.

  • Actions

    Closed


    Closed


    Deadline was:

    A-6: Perform rig survey and identify interface for new installed equipment

    Rig surveys performed for non incumbent services from service provides. Soiltech, Roxar, SLB, Expro and Halliburton performed the rig survey and report distributed for follow-up and close out. No further followu-up required towards SLB and Roxar. Expro CLMA technology not selected for Bestla – no further follow-up required. Halliburton required further follow up and will be managed through the weekly follow-up meetings with the Bestla D&W teams. Soiltech interface findings to be followed up with Sval in project meetings after the report is issued end of February.

  • Actions

    Closed


    Closed


    Deadline was:

    Verification of the crane and lifting routines identified a gap in the capability of the offshore Technical responsible to perform his duties towards verification of documenation and certification of lifting equipment provided by all parties to DSY. Weak organizational barrier which could lead to incidents or accidents.

    A-7: To perform the operator’s “see it” duty, it is strongly recommended to perform onshore verification of lifting equipment and documentation by a competent third party before lifting equipment is mobilised offshore and documented through a compliance certificate form the competent third party.

    Experience transfer meeting with Vår Energi arranged to exchnge the experiences from the onshore lifting verification process implemented by VE after a serious dropped object incident during the PP&A campaign on Jotun. Learning from incidents and accidents is key to ensure avaoidance of re-occurance and hence why the intention is to duplicate the verification process implemented by Vår Energi.
    Conclusion from meeting: Lifting verification to be implemented on both OKEA and Sval operations and quote requested from Oceaneering Asset Integrity
    Action closed in this rig intake and verification to be implemented upon issue of PO. Quote received and accepted by both Sval and OKEA.

  • Actions

    Closed


    Closed


    Deadline was:

    A-8: Evaluate need for additional air monitoring (add on to Furuno)

    Odfjell has implemented a operational practice / guideline on how to manage drone activity.
    No further actions taken as the drone activity on the NCS has declined. Should drone activity increase over time this add-on technology will be further evaluated.

  • Actions

    Open

    Open
    Deadline was:

    ROREPA is based on previous version of the QRA/CORA. Newer edition of the QRA is under development and therefore it needs to be assessed wehtehr those changes require a update of the RORAPA which has been issued for use.

    A-9: Evaluate to update Review ROREPA based on updated QRA and SSREPA

  • Actions

    Closed


    Closed


    Deadline was:

    A-10a: OKEA Marine and base manager Morten Veiset to verify the hook and lifting ring on PSV on contract with the logistics pool from OKEA
    A-10b: WE logistics Johan Kjos to verify the hook and lifting ring on PSV that will come on contract for the SVAL PP&A operations.

    DSY has a Henriksen lifting ring see attached.
    On Bestla there is no requirements towards a dedicated standaby vessel or PSV therefore this actions is closed.

  • Actions

    Open

    Open
    Deadline was:

    A-11: RUG Matrix in place but must be updated – follow up. GHRV been postponed

  • Actions

    Open

    Open
    Deadline was:

    A-12: Establish NORM testing procedures and training and have necessary testing equipment available during PP&A campaign Vale. Train personnel in testing.

    OD personnel on the rig trained for NORM testing. Final competence verification to be performed 1 month before commencement date of the rig contract on Vale.

  • Actions

    Closed


    Closed


    Deadline was:

    Section milling is a potential tertiary contingency solution. This operations has never been conducted on DSY and hence why a swarf handling risk assessment is to be required during the pre-operational planning phase.

    A-13: Conduct swarf risk assessment for Vale

    Swarf Risk assessment Incorporated in the integrated project plan for Sval and this plan will be followed-up in bi-weekly meetings. No further follow-up in this ARV plan.

  • Actions

    Closed


    Closed


    Deadline was:

    A-14: WSOG to be prepared by Odfjell

    Mooring and riser analysis established for OKEA Bestla – WSOG received see attached

  • Actions

    Open

    Open
    Deadline was:

    A-15a: OKEA Marine and base manager Morten Veiset to follow up and verify that the DP trial is performed is performed before spud on Bestla.
    A-15b: WE Marine advisor Stian Engvik to follow up and verify that the DP trial is performed is performed before commencement of operations on Vale.

    15A – DP trial to be performed when rig is on contract with OKEA and before top holes are to be drilled on DP.

  • Actions

    Closed


    Closed


    Deadline was:

    Mooring lines on both Vale and Bestla are shallow due to the water depth at this location. Collision between visiting PSV vessels and the shallow mooring lines can be avoid by installing Nav-packs on the visiting PSV ounder contract during both Sval and OKEA operations.

    A-16a: OKEA Marine and manage manager Morten Veiset to evaluate to have the PSV`s be fitted with NAV-Pack from rig pos. supplier to visually have dynamic updates of mooring lines to avoid contact with mooring lines during OKEA Operations
    A-16B: Marine advisor Stian Engvik evaluate to have the PSV`s be fitted with NAV-Pack from rig pos. supplier to visually have dynamic updates of mooring lines to avoid contact with mooring lines during Sval operations

    Response from OKEA: Navpack evaluated with OKEA vessel captains on contract. Marine personnel do not see the value of this as the same objective can be achieved through the Master standing Order in combination with the DSY datasheet which visualizes the mooring spread on the location. Additionally with OKEA joining the NLP project in principle no dedicated vessels are planned for. Instead the main logistics supply stratgey is managed through a logistics pool with several vessels suplying the operations in the Tampen area. Having Navpacks instaled on al vessels is seen not doable.

  • Actions

    Closed


    Closed


    Deadline was:

    Odfjell does not periodically perform the drawdown test as per Norsok D-001 which refers to API 53. Not required in Norsok D-010. A drawdown test as per D-001 is to be perfromed as part as the first pre-deployment test before commencement of operations on Bestla Development.

    A-17: Accumulator drawdown test to be performed before the BOP is installed on the WH on Bestla

    Drawdown test to be performed before BOP deployment on Bestla and included in well control bridging document

  • Actions

    Closed


    Closed


    Deadline was:

    Risk ID 10 and 11.
    Cyber security.
    Verify adequate IT security/firewalls

    OKEA and Sval IT to validate Odfjell / Starlink IT system through a verification.
    OKEA/ SVAL IT to verify firewall system maintained through Speedcast / Option

    Verification perfromed by OKEA IT towards OD and Oceaneering. New remote scope identified towards Baker Hughes for remote operating tractor and a verification towards Cyber security is agreed to be included but pending. Baker IT verification performed and report issued for approval . Doc no OKEA-BRS-ITI-REP-0279.

  • Actions

    Closed


    Closed


    Deadline was:

    Risk ID 22.
    Medical preparedness evaluation to becompleted by OKEA company doctor

    OKEA Company doctor to verify medical preparedness:
    – check of hospital, pharmaceutical routines, EKG routines and medevac procedures.
    – Review relevant documentation
    – Assess need for offshore verification

    OKEA company doctor report received and issued to OD for review.
    Sval company doctor attachement to AfC pending. Received and included in AfC.

  • Actions

    Open

    Open
    Deadline was:

    Risk ID 31.
    Station keeping.

    OKEA – DP vessel intake verification to be performed as per OKEA BMS
    OKEA/SVAL – OVID certification review – if no valid OVID certificate in place, OVID inspection to be performed as part of the rig intake scope by SVAL/OKEA

    OVID perfromed Q1-2025 and certificate available on OVID database.



Additional Documentation


MOM-Joint-Rig-Intake-Risk-Assessment.pdf, DSY-Rig-intake-Risk-register-Jan-2025.xlsx, Lifting-ring.pdf, OKEA-BRS-ITI-REP-0279-Bestla-information-security-review.pdf, L4-MODU-DSY-E-MA-325-30-WSOG-DP-Tophole-Bestla-Rev.0.xlsx, L4-MODU-DSY-E-MA-325-31-WSOG-Posmoor-Bestla-Rev.0.xlsx




New Audit Report

You do not have permission to view this form.


\n


Rig Intake

No person selected

Report No.

7957
Rig Intake Risk Assessment

Type of audit

Rig Intake
Rig Intake

Auditee/Customer

Rig Intake
OKEA/SVAL

Date

2025/01/22

319 days ago

Findings

20
Number of findings

Status

In process
Rig Intake


Rig Intake Risk Assessment
Summary

OKEA ASA (OKEA) and SVAL Energy AS (SVAL) has completed the rig selection process and have established an agreement with Odfjell Drilling (Odfjell) to utilise the rig Deepsea Yantai (DSY). OKEA and Sval have made an agreement to carry out a joint rig intake for Deepsea Yantai. OKEA is planning to drill two production wells on Bestla and Sval will Plug & permanent Abandon the Vale well. OKEA will be the first operator with a commencement window for the DSY between July 1st, 2025, and December 31st, 2025. Well Expertise (WE) has been contracted to lead the rig intake process on behalf of OKEA and Sval.
A Rig Intake Risk Assessment was carried out on Teams 16.01.2025.
The participants identified totally 33 risks, however only 10 risks are medium after compensating measures and will have special focus in the rig intake process. The medium risks will be included in the rig intake plan. No residual risks were classified as red.
17 actions were identified and discussed and followed up in this report.

Findings

  • Actions

    Open

    Open
    Deadline was:

    A-1a: OKEA IT Erwin Geis Establish contract with Speedcast with back-up solution for OKEA operations
    A-1b: WE Lars Solvang Establish contract with Speedcast through Odfjell with back-up solution

    1A:OKEA IT contract established with Options AS for both Starlink communications and IT. Action closed for OKEA
    1B:Pending action Lars Solvang to establish agreement for Sval PP&A scope with earliest commencement 1.1.25 – Due date extended to meet Sval commencement date.

  • Actions

    Open

    Open
    Deadline was:

    A-2a: OKEA IT Erwin Geis to ensure back-up solution to Speedcast (VSAT or equivalent) for OKEA operations
    A-2b: WE Lars Solvang to ensure back-up solution to Speedcast (VSAT or equivalent) for Sval operations

    2A:OKEA IT contract established with Options AS for both Starlink communications and IT. Back-up solution LTE agreed and included in the contract. Action closed for OKEA
    2B:Pending action Lars Solvang to establish agreement for Sval PP&A scope with earliest commencement 1.1.25 – Due date extended to meet Sval commencement date.

  • Actions

    Open

    Open
    Deadline was:

    A-3a:OKEA Logistics and base manager Morten Veiset to ensure that Inspection services are incorporated incorporated in logistics base contract scope of work for OKEA operations
    A-3b:WE Logistics Johan Kjos to ensure that Inspection services are incorporated incorporated in logistics base contract scope of work for Sval operations

    3A – Confirmed included in OKEA base contract – OKEA action closed
    3B – Pending due date extended to meet Sval commencement date

  • Actions

    Open

    Open
    Deadline was:

    Roel/Johan: A-4:L3-MODU-ALL-TO-PR-016 Temporary Equipment to be sent out to service companies.
    Karina/Morten: Ensure third party equipment is according to working environment requirements.
    Roger/DSV: Ensure that equipment is included in the rigs maintenance system

  • Actions

    Closed


    Closed


    Deadline was:

    A-5: Make sure that routines are in place for Cement unit handover between wells – review handover documentation (Baker cement unit) and verify cement unit maintenance system towards SLB

    Maintenenace review scheduled for Apil 2nd. Handover meeting confirmed by SLB.
    Maintenance review identified several observation. Action closed here and follow-up in ARV report 8537.

  • Actions

    Closed


    Closed


    Deadline was:

    A-6: Perform rig survey and identify interface for new installed equipment

    Rig surveys performed for non incumbent services from service provides. Soiltech, Roxar, SLB, Expro and Halliburton performed the rig survey and report distributed for follow-up and close out. No further followu-up required towards SLB and Roxar. Expro CLMA technology not selected for Bestla – no further follow-up required. Halliburton required further follow up and will be managed through the weekly follow-up meetings with the Bestla D&W teams. Soiltech interface findings to be followed up with Sval in project meetings after the report is issued end of February.

  • Actions

    Closed


    Closed


    Deadline was:

    Verification of the crane and lifting routines identified a gap in the capability of the offshore Technical responsible to perform his duties towards verification of documenation and certification of lifting equipment provided by all parties to DSY. Weak organizational barrier which could lead to incidents or accidents.

    A-7: To perform the operator’s “see it” duty, it is strongly recommended to perform onshore verification of lifting equipment and documentation by a competent third party before lifting equipment is mobilised offshore and documented through a compliance certificate form the competent third party.

    Experience transfer meeting with Vår Energi arranged to exchnge the experiences from the onshore lifting verification process implemented by VE after a serious dropped object incident during the PP&A campaign on Jotun. Learning from incidents and accidents is key to ensure avaoidance of re-occurance and hence why the intention is to duplicate the verification process implemented by Vår Energi.
    Conclusion from meeting: Lifting verification to be implemented on both OKEA and Sval operations and quote requested from Oceaneering Asset Integrity
    Action closed in this rig intake and verification to be implemented upon issue of PO. Quote received and accepted by both Sval and OKEA.

  • Actions

    Closed


    Closed


    Deadline was:

    A-8: Evaluate need for additional air monitoring (add on to Furuno)

    Odfjell has implemented a operational practice / guideline on how to manage drone activity.
    No further actions taken as the drone activity on the NCS has declined. Should drone activity increase over time this add-on technology will be further evaluated.

  • Actions

    Open

    Open
    Deadline was:

    ROREPA is based on previous version of the QRA/CORA. Newer edition of the QRA is under development and therefore it needs to be assessed wehtehr those changes require a update of the RORAPA which has been issued for use.

    A-9: Evaluate to update Review ROREPA based on updated QRA and SSREPA

  • Actions

    Closed


    Closed


    Deadline was:

    A-10a: OKEA Marine and base manager Morten Veiset to verify the hook and lifting ring on PSV on contract with the logistics pool from OKEA
    A-10b: WE logistics Johan Kjos to verify the hook and lifting ring on PSV that will come on contract for the SVAL PP&A operations.

    DSY has a Henriksen lifting ring see attached.
    On Bestla there is no requirements towards a dedicated standaby vessel or PSV therefore this actions is closed.

  • Actions

    Open

    Open
    Deadline was:

    A-11: RUG Matrix in place but must be updated – follow up. GHRV been postponed

  • Actions

    Open

    Open
    Deadline was:

    A-12: Establish NORM testing procedures and training and have necessary testing equipment available during PP&A campaign Vale. Train personnel in testing.

    OD personnel on the rig trained for NORM testing. Final competence verification to be performed 1 month before commencement date of the rig contract on Vale.

  • Actions

    Closed


    Closed


    Deadline was:

    Section milling is a potential tertiary contingency solution. This operations has never been conducted on DSY and hence why a swarf handling risk assessment is to be required during the pre-operational planning phase.

    A-13: Conduct swarf risk assessment for Vale

    Swarf Risk assessment Incorporated in the integrated project plan for Sval and this plan will be followed-up in bi-weekly meetings. No further follow-up in this ARV plan.

  • Actions

    Closed


    Closed


    Deadline was:

    A-14: WSOG to be prepared by Odfjell

    Mooring and riser analysis established for OKEA Bestla – WSOG received see attached

  • Actions

    Open

    Open
    Deadline was:

    A-15a: OKEA Marine and base manager Morten Veiset to follow up and verify that the DP trial is performed is performed before spud on Bestla.
    A-15b: WE Marine advisor Stian Engvik to follow up and verify that the DP trial is performed is performed before commencement of operations on Vale.

    15A – DP trial to be performed when rig is on contract with OKEA and before top holes are to be drilled on DP.

  • Actions

    Closed


    Closed


    Deadline was:

    Mooring lines on both Vale and Bestla are shallow due to the water depth at this location. Collision between visiting PSV vessels and the shallow mooring lines can be avoid by installing Nav-packs on the visiting PSV ounder contract during both Sval and OKEA operations.

    A-16a: OKEA Marine and manage manager Morten Veiset to evaluate to have the PSV`s be fitted with NAV-Pack from rig pos. supplier to visually have dynamic updates of mooring lines to avoid contact with mooring lines during OKEA Operations
    A-16B: Marine advisor Stian Engvik evaluate to have the PSV`s be fitted with NAV-Pack from rig pos. supplier to visually have dynamic updates of mooring lines to avoid contact with mooring lines during Sval operations

    Response from OKEA: Navpack evaluated with OKEA vessel captains on contract. Marine personnel do not see the value of this as the same objective can be achieved through the Master standing Order in combination with the DSY datasheet which visualizes the mooring spread on the location. Additionally with OKEA joining the NLP project in principle no dedicated vessels are planned for. Instead the main logistics supply stratgey is managed through a logistics pool with several vessels suplying the operations in the Tampen area. Having Navpacks instaled on al vessels is seen not doable.

  • Actions

    Closed


    Closed


    Deadline was:

    Odfjell does not periodically perform the drawdown test as per Norsok D-001 which refers to API 53. Not required in Norsok D-010. A drawdown test as per D-001 is to be perfromed as part as the first pre-deployment test before commencement of operations on Bestla Development.

    A-17: Accumulator drawdown test to be performed before the BOP is installed on the WH on Bestla

    Drawdown test to be performed before BOP deployment on Bestla and included in well control bridging document

  • Actions

    Closed


    Closed


    Deadline was:

    Risk ID 10 and 11.
    Cyber security.
    Verify adequate IT security/firewalls

    OKEA and Sval IT to validate Odfjell / Starlink IT system through a verification.
    OKEA/ SVAL IT to verify firewall system maintained through Speedcast / Option

    Verification perfromed by OKEA IT towards OD and Oceaneering. New remote scope identified towards Baker Hughes for remote operating tractor and a verification towards Cyber security is agreed to be included but pending. Baker IT verification performed and report issued for approval . Doc no OKEA-BRS-ITI-REP-0279.

  • Actions

    Closed


    Closed


    Deadline was:

    Risk ID 22.
    Medical preparedness evaluation to becompleted by OKEA company doctor

    OKEA Company doctor to verify medical preparedness:
    – check of hospital, pharmaceutical routines, EKG routines and medevac procedures.
    – Review relevant documentation
    – Assess need for offshore verification

    OKEA company doctor report received and issued to OD for review.
    Sval company doctor attachement to AfC pending. Received and included in AfC.

  • Actions

    Open

    Open
    Deadline was:

    Risk ID 31.
    Station keeping.

    OKEA – DP vessel intake verification to be performed as per OKEA BMS
    OKEA/SVAL – OVID certification review – if no valid OVID certificate in place, OVID inspection to be performed as part of the rig intake scope by SVAL/OKEA

    OVID perfromed Q1-2025 and certificate available on OVID database.



Additional Documentation


MOM-Joint-Rig-Intake-Risk-Assessment.pdf, DSY-Rig-intake-Risk-register-Jan-2025.xlsx, Lifting-ring.pdf, OKEA-BRS-ITI-REP-0279-Bestla-information-security-review.pdf, L4-MODU-DSY-E-MA-325-30-WSOG-DP-Tophole-Bestla-Rev.0.xlsx, L4-MODU-DSY-E-MA-325-31-WSOG-Posmoor-Bestla-Rev.0.xlsx



\n”}}]}]}]},{“type”:”section”,”props”:{“class”:”uk-hidden”,”id”:”newreport”,”image_position”:”center-center”,”padding”:”none”,”style”:”default”,”title_breakpoint”:”xl”,”title_position”:”top-left”,”title_rotation”:”left”,”vertical_align”:””,”width”:”default”},”children”:[{“type”:”row”,”children”:[{“type”:”column”,”props”:{“image_position”:”center-center”,”position_sticky_breakpoint”:”m”},”children”:[{“type”:”html”,”props”:{“content”:”

\n

\n

New Audit Report