Summary

PUN performed a review of Schlumberger WC (SLB) focusing on planning and
readiness related to slop treatment and cuttings handling. SLB gave a systematic presentation on the topics requested by the review team and according to the agenda.
The review team identified one (1) non-conformance, no (0) improvement points, one (1) observation, and 9 actions.

Findings

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    SLB’s Measuring Program (TP-ESNOR-561-0559-Q-069) describes Envirounit STU. This unit uses
    chemicals for slop treatment and are based on two different technologies. On DSY they use an
    OTS STU where no chemicals are used.

    SLB to develop a measurement program for the Onsite Treatment Services (OTS) Slop Treatment Unit (STU) onboard Deepsea Yantai.

    26.09.22: Measurement program received

  • Improvement

    Closed


    Closed


    Deadline was:

    In presentation SLB showed that the OTS STU discharged OiW below 30 ppm

    AS 30 ppm is a requirement and everyone ensure that they are within that, the review team challenge SLB to show average ppm in presentations, to get a better understanding of the OTS STU’s performance (selling point).

    25.08.22: SLB response – Future presentation will contain a better presentation of the ppm average.

  • Actions

    Closed


    Closed


    Deadline was:

    SLB to share presentation

    Presentation received 22.06.22

  • Actions

    Closed


    Closed


    Deadline was:

    Consider using ISO tanks as standard for
    future ops

    The ISO tanks was onboard, but PUN decided to go for skip & ship. As an good ESG initiative to reduce CO2 emission, ISO hose management is a much better alternative than skip management.

    It is discussed and considered as part of rig intake of DSY for Wellesley and DNO.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure that skip loading station is onboard before start-up of Copernicus and needed pipework installed

    25.08.22: Status – SLS is delivered in Florø along with container to be put on the spud boat for delivery to DSY. Deadline is set for before start up of 12 ½’’ section (05.09.2022 according to Kabal)
    10.09.22: All good

  • Actions

    Closed


    Closed


    Deadline was:

    SLB to send daily waste and slop reports to environmental@wellexpertise.com

    Reports received when the Copernicus operation started

  • Actions

    Closed


    Closed


    Deadline was:

    Sea fastening must be a checkpoint in DOP
    (securing any loose items – check)

    Included when started sailing

  • Actions

    Closed


    Closed


    Deadline was:

    Bring forward to Phil to check with
    Neptune/Odfjell the slops unit air
    compressors and centrifuge will all stay
    on the rig for the move from Ophelia to
    Copernicus (in transit draft)

    30.06.22: Centrifuge is staying. Air compressors lift on off relatively easy and they will be demobilised due to VDL limits and will be remobilised via Sandnesjøen.

  • Actions

    Closed


    Closed


    Deadline was:

    Skip logistics need to be coordinated,
    QA of skips integrity before backloaded

    Skips handling was coordinated with SLB throughout the whole operation and QA were performed before backload of every skip.

  • Actions

    Closed


    Closed


    Deadline was:

    Are there any ESG initiatives affecting
    the Copernicus ops? If possible, nice to
    get documentation. SLB to check and
    have this in your mind for future expl.
    drilling ops.

    23.08.22: Asked for updates
    25.08.22:
    – SLB have proposed use of ISO pump to improve working environment, HSE and CO2.
    – SLB have also offered PGNiG to use the ATC truck for cleaning tanks on the PSV, to re-use wash water, and minimize slop generated for clean up job. By use of this ATC unit also minimize the personnel for entering tanks.

    For the Copernicus project there were no ESG initiative from SLB ES.

  • Actions

    Closed


    Closed


    Deadline was:

    Send self-assessment scheme related
    to Transparency Act (sent to suppliers).

    Received 08.07.22.



Additional Documentation

WE-EA-2022-02-Review-Report-Schlumberger-slop-and-cuttings_-signed.pdf


WE-EA-2022-02-Review-Report-Schlumberger-slop-and-cuttings_-signed.pdf




New Audit Report

You do not have permission to view this form.


\n


Schlumberger

No person selected

Report No.

4777
Review Schlumberger slop and cuttings

Type of audit

External Audits
Schlumberger

Auditee/Customer

Schlumberger
PGNiG Upstream Norway AS

Date

2022/06/21

1266 days ago

Findings

11
Number of findings

Status

Closed
External Audits


Review Schlumberger slop and cuttings
Summary

PUN performed a review of Schlumberger WC (SLB) focusing on planning and
readiness related to slop treatment and cuttings handling. SLB gave a systematic presentation on the topics requested by the review team and according to the agenda.
The review team identified one (1) non-conformance, no (0) improvement points, one (1) observation, and 9 actions.

Findings

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    SLB’s Measuring Program (TP-ESNOR-561-0559-Q-069) describes Envirounit STU. This unit uses
    chemicals for slop treatment and are based on two different technologies. On DSY they use an
    OTS STU where no chemicals are used.

    SLB to develop a measurement program for the Onsite Treatment Services (OTS) Slop Treatment Unit (STU) onboard Deepsea Yantai.

    26.09.22: Measurement program received

  • Improvement

    Closed


    Closed


    Deadline was:

    In presentation SLB showed that the OTS STU discharged OiW below 30 ppm

    AS 30 ppm is a requirement and everyone ensure that they are within that, the review team challenge SLB to show average ppm in presentations, to get a better understanding of the OTS STU’s performance (selling point).

    25.08.22: SLB response – Future presentation will contain a better presentation of the ppm average.

  • Actions

    Closed


    Closed


    Deadline was:

    SLB to share presentation

    Presentation received 22.06.22

  • Actions

    Closed


    Closed


    Deadline was:

    Consider using ISO tanks as standard for
    future ops

    The ISO tanks was onboard, but PUN decided to go for skip & ship. As an good ESG initiative to reduce CO2 emission, ISO hose management is a much better alternative than skip management.

    It is discussed and considered as part of rig intake of DSY for Wellesley and DNO.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure that skip loading station is onboard before start-up of Copernicus and needed pipework installed

    25.08.22: Status – SLS is delivered in Florø along with container to be put on the spud boat for delivery to DSY. Deadline is set for before start up of 12 ½’’ section (05.09.2022 according to Kabal)
    10.09.22: All good

  • Actions

    Closed


    Closed


    Deadline was:

    SLB to send daily waste and slop reports to environmental@wellexpertise.com

    Reports received when the Copernicus operation started

  • Actions

    Closed


    Closed


    Deadline was:

    Sea fastening must be a checkpoint in DOP
    (securing any loose items – check)

    Included when started sailing

  • Actions

    Closed


    Closed


    Deadline was:

    Bring forward to Phil to check with
    Neptune/Odfjell the slops unit air
    compressors and centrifuge will all stay
    on the rig for the move from Ophelia to
    Copernicus (in transit draft)

    30.06.22: Centrifuge is staying. Air compressors lift on off relatively easy and they will be demobilised due to VDL limits and will be remobilised via Sandnesjøen.

  • Actions

    Closed


    Closed


    Deadline was:

    Skip logistics need to be coordinated,
    QA of skips integrity before backloaded

    Skips handling was coordinated with SLB throughout the whole operation and QA were performed before backload of every skip.

  • Actions

    Closed


    Closed


    Deadline was:

    Are there any ESG initiatives affecting
    the Copernicus ops? If possible, nice to
    get documentation. SLB to check and
    have this in your mind for future expl.
    drilling ops.

    23.08.22: Asked for updates
    25.08.22:
    – SLB have proposed use of ISO pump to improve working environment, HSE and CO2.
    – SLB have also offered PGNiG to use the ATC truck for cleaning tanks on the PSV, to re-use wash water, and minimize slop generated for clean up job. By use of this ATC unit also minimize the personnel for entering tanks.

    For the Copernicus project there were no ESG initiative from SLB ES.

  • Actions

    Closed


    Closed


    Deadline was:

    Send self-assessment scheme related
    to Transparency Act (sent to suppliers).

    Received 08.07.22.



Additional Documentation

WE-EA-2022-02-Review-Report-Schlumberger-slop-and-cuttings_-signed.pdf


WE-EA-2022-02-Review-Report-Schlumberger-slop-and-cuttings_-signed.pdf



\n”}}]}]}]},{“type”:”section”,”props”:{“class”:”uk-hidden”,”id”:”newreport”,”image_position”:”center-center”,”padding”:”none”,”style”:”default”,”title_breakpoint”:”xl”,”title_position”:”top-left”,”title_rotation”:”left”,”vertical_align”:””,”width”:”default”},”children”:[{“type”:”row”,”children”:[{“type”:”column”,”props”:{“image_position”:”center-center”,”position_sticky_breakpoint”:”m”},”children”:[{“type”:”html”,”props”:{“content”:”

\n

\n

New Audit Report