Rig Intake Review Report

Type of audit

Rig Intake
Odfjell Drilling

Auditee/Customer

Odfjell Drilling
Wellesley/DNO

Date

2022/12/21

1083 days ago

Findings

40
Number of findings

Status

Closed
Rig Intake


Rig Intake Review Report
Summary

As a part of rig intake and preparations for Wellesley’s and DNO’s exploration wells, Carmen and Norma, an onshore review was held with Odfjell 2nd of December 2022. The review was held at Odfjell’s premises at Kokstadflaten 35 in Bergen.
The review was held in a good atmosphere, the Odfjell participants were very open and willing to explain and share information.
The review team identified two (2) non-conformances, one (1) observation and seven (7) improvement points. The findings are listed in Section 4.
Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.
The review team’s impression is that Odfjell is a rig company that has a well-functioning business management system. Odfjell is ISO 9001 (Quality Management), ISO 14001 (Environmental Management) certified, and the management system is also prepared according to ISO 45001 (Occupational Health and Safety Management) and ISO 50001 (Energy Management). A separate competence review will be scheduled closer to spud on Carmen.

Findings

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    Vaptreat is presented with yellow colour category, but shall be red

    Update Measurement program. Check chemical registration system and update.

    Measurement program is updated with Vaptreat as red colour code. The chemical is also nominated for substitution.

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    L4-MODU-DSY-E-MA-506 Rig specific measurement program is not according to requirements. The description of the chemical treatment system (wrong slop unit etc.) is incorrect.

    Update measurement program

    Synergi 229018
    The masurement program was updated in January 2023 but still som information is missing. – The discharge of BOP fluid not updated to reflect discharges through slop treatment unit (small amounts). The Figure in Ch. 3.1.2 states discharges, but the text still says differently: When it is on deck the BOP fluid can be taken in return through the FRU (Fluid recovery unit) or to slop tank and sent onshore
    – and discharge factor.
    – Additional information should be given regarding usage of Rena unit. Should say that this is a back up system that the client usally have a slop unit onboard.
    – Koper-cote is not included in the program (used on the well head connector, not discharged to sea).
    – Environmental verification 19.-21. april revelaed that the measurement program needs to be updated furter. Some chemicals are missing.

    This action will be followed up in WE Report 5218.

  • Observation

    Closed


    Closed


    Deadline was:

    Insufficient registration/logging of – MOB boat/FRC training. The Exercise and training report are insufficient. The report lacks information on what was done during the training, and it also states the same time for starting and completing of the training.

    The registration/ logging of the training should be according to the training directive.

    19.01.2023 JKAA.  As described, discrepancy between the drill matrix and the actual logged drills/training were observed.  Routines for weekly follow up by SSL is established to ensure that all exercises/training tasks has been met and to ensure quality of logging including the evaluation and corrective actions in case of Performance standar not beeing met.  Routines for exercise follow up by SSL is established in revised CMS ” Verifikasjon og logging av Øvelser i Rig Manager CMS 82051.  And a new Excel file has been made to to cross check training matrix against drills reported in rig manager.  This will make it possible to pinpoint every crewmembers training records for tjhe last 2.5 years

  • Improvement

    Closed


    Closed


    Deadline was:

    Top of helideck skid to be repainted with tiger stripes

    Repaint helideck skid

    Helideck skid has been repainted with tiger stripes. verified during rig inspection 23 January 2023.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider including HPHT competence in competence matrix for drilling personnel

    Ref. synergi 229021

    ANKJ- 04.01.23 We think this is a good suggestion and we will include this in training matrix
    when we have a sollution. We will ask Sven Hope regarding this.
    ÅKP 22.05.23: Still open need to postpone deadline
    ÅKP: 01.08.2023 This i closed in Synergi. The case is with HR and will ble implemented. Case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider providing role familiarization for Safety Delegate

    Have been followed up in synergi 229021

    The safety delegate role will not be included in the familiarization scheme, however there is a VO guideline: L2-NO-HSE-GL-009N that describes the tasks. Spoke to safety delegate from service during Rig visit 23.01.2023. and he said he got a good introduction to the safety delagate role. They have a SD meeting very Fridays and he has 4 hours every week to work with H&S. The HVO has 8 hours every week.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider providing role familiarization for Environmental Officer

    Synergi 229021

    The TSL has been provided training for the role as environmental officer. This is stated in the procedure L3-MODU-ALL-JD-003-017

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider substituting the chemical Vaptreat (red) with SCAL16075A (yellow)

    Vaprtreat is on the substitution list and will be replaced with SCAL16075A during 2023.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider substituting the chemical Jet-Lube HPHT (yellow Y2) with Jet-Lube Seal Guard (yellow)

    20.02.23:
    This product will not be substituted due to technical and security reasons. Manufacturer does not approve that.
    The product will only be used when needed, not regularly.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider preparing a procedure for handling of drones within 500m zone

    Ref. synergi 229021

    Odfjell has a action plan for management of drones. This is also included in tabletops. Details for reporting is included in Emergency Preparedness bridging document

  • Actions

    Closed


    Closed


    Deadline was:

    Send over presentation from meeting

    Received presentation

  • Actions

    Closed


    Closed


    Deadline was:

    Send updated org. chart for onshore organisation

    Received updated org. charts

  • Actions

    Closed


    Closed


    Deadline was:

    Send an overview of internal deviations registered in synergy

    Received status as pr. 22.20.23

  • Actions

    Closed


    Closed


    Deadline was:

    Inform Bristow on the non-con on 4 cm on helideck

    Bristow informed

  • Actions

    Closed


    Closed


    Deadline was:

    Please provide plans for HMS helideck repeater lights

    Helideck repeater lights are installed and verified during rig visit 23-24 january

  • Actions

    Closed


    Closed


    Deadline was:

    Send QHSE plan and KPI’s

    Synergi 229021

    QHSE Action plan for DSY received

  • Actions

    Closed


    Closed


    Deadline was:

    Send a copy of the Audit Plan for 2023

    Audit plan is received.

  • Actions

    Closed


    Closed


    Deadline was:

    Send Crew rotation plan with legend, explaining the colours

    Received

  • Actions

    Closed


    Closed


    Deadline was:

    Secure proper training on HPHT, and that personnel with HPHT experience are evenly represented in all crews. e.g. crew B

    27.06.2023 Closed

  • Actions

    Closed


    Closed


    Deadline was:

    Send copies of: MODU-ALL-TO-PR-016 Procedure for temporary equipment, L-3-MODU-ALL-QU-PR-034 Procedure for management of service providers on MODU’s, including attachments, The units third party and temporary equipment standard. This is for the operator to forward to service providers.

    synergi 229227

    The documents are received.

  • Actions

    Closed


    Closed


    Deadline was:

    Forward Health and Working environment Plan for 2023

    Received, Synergi 229227

  • Actions

    Closed


    Closed


    Deadline was:

    Invite Åse to AMU meeting in March (and June)

    Åse has received the invitation, but OMV will participate since they have the rig.

  • Actions

    Closed


    Closed


    Deadline was:

    Prepare simulations of oil mist and vapor

    Decided that this is not necessary, personnel will only be exposed for vapour/mist in the shaker room.

  • Actions

    Closed


    Closed


    Deadline was:

    Send a copy of latest Working environment surveys (Noise and Chemical)

    24.06.2023 Received noise report, waiting for chemical
    08.07.2023 Chemical Health Risk Assessment received

  • Actions

    Closed


    Closed


    Deadline was:

    Set a date for a working environment meeting discussing mitigation measures for management of OBM fumes together with occupational health services.

    A working environment meeting has been held, see mom attached

  • Actions

    Closed


    Closed


    Deadline was:

    Secure that temporary equipment is according to Z-015 and S-002 and according to Odfjell requirement

    Information was provided to logistics coordinators for the various service providers.

  • Actions

    Closed


    Closed


    Deadline was:

    SD to be chosen for Crew B from 4S and courses to be schedule

    Closed. Synergi 229227 – Info received 24.03.2023. all crews have a safety delegate

  • Actions

    Closed


    Closed


    Deadline was:

    Odfjell to collect experience from other rigs and purchase screen washer.

    DSN is testing, get information from DSN

    22.05.23 ÅKP Still outstanding, need to postpone deadline
    08.12.2023. • VI har pr i dag en screenwasher men vi undersøker hvilke modeller som er mest egnet et DSY pga brukervennlighet og best egnet plassering i shaker)
    19.02.2024 Followed up in 5968-A10

  • Actions

    Closed


    Closed


    Deadline was:

    Send over a recommendation from Valhall on screen washer

    Sent over recommendation, see attached mail

  • Actions

    Closed


    Closed


    Deadline was:

    Mark power tools with exposure limits

    Synergi 229227. Tools are marked according to procedure

  • Actions

    Closed


    Closed


    Deadline was:

    Send over copy of a report where the FRC from PSV/SBV was lifted to the rig

    Synergi 229227, have revied an overview of exercises. The rig confirms training with the FRC from Siddis Mariner but have not logged the report in Rig manager.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure an overview of f-gases in monthly reports (ref. finding from last verification)

    Synergi 229227. Reveived 23.03.23

  • Actions

    Closed


    Closed


    Deadline was:

    Send over chemical substitution plan for 2023

    Synergi 229227. Reveived 23.03.23

  • Actions

    Closed


    Closed


    Deadline was:

    Send HAZID for pipe handling matrix from 2022

    Received and updated hazid work sheet, but need the report with participants, etc
    17.07.2023 Awaiting New HAZID report, need to postpone deadline.

    Åse: 01.08.2023 Received ny HAZID report. Case closed

  • Actions

    Closed


    Closed


    Deadline was:

    Non-con regarding mooring lines (DNV class 61) – an area on the wires is in poor condition. Mooring line 1,2,5 and 7 to be re-evaluated.

    Mooring lines changed out, DNV is currently approving the documentation (Conditions of class)

  • Actions

    Closed


    Closed


    Deadline was:

    Info/documentation of BOP cutting test of 17” liner/casing

    Synergi 229227
    See DAS for Casing Shear Ram. Cut test are owned by Equinor.
    Operator to decide if testing is to be done and paid for. Or pay Equinor to get access to their report.

  • Actions

    Closed


    Closed


    Deadline was:

    BOP RA incl. LFS5 (one set will arrives 02.02.23, 2 sets 13.04.23). Call for a BOP ram risk assessment

    11.10.23-SS.: BOP Risk Assessment held prior to both Carmen (31.03.23) and Norma (07.06.23). 3 sets of LFS5 are available.

  • Actions

    Closed


    Closed


    Deadline was:

    Answer to Appendix B in PUN report, actions taken
    Copy of 225623.225624, 227024, 227006, 227007, 226999, 227012

    225623 – KPI’s are not measureble
    225624 – Follow up of Environmental aspects and impacts
    226999 – Drillpipes outside bounded area
    227007- Storage of waste in wooden crates
    227012 – Training in detection of spill
    227024 – Signage exiting accommodation
    227006 –

    225623 – KPI’s are now measurable (Closed)
    225624 – Shall be included in the QHSE program and DSY action plans (closed)
    22699 – Area is painted and information posted on a sign (closed)
    227007 –Use IBC (Closed)
    227012 – Since VISSIM is not used onboard at the time Odfjell will postpone this training. OMW is using Safepath and Wellesley, DNO and PUN SmartBlue. (closed)
    227024 – 13.08.22: JKAA Sign on every door leading in/out from changeroom to maindeck is in
    place (closed)
    227006 – Followed up in separate action.

  • Actions

    Closed


    Closed


    Deadline was:

    Present use of lifting coach, scope of work

    Scope is presented to odfjell and the operators. Lifting coach is book out during March.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure coms, radio survey

    Coms secured once on location.



Additional Documentation


Screen-washer.pdf, WE-EA-2022-03-Rig-Intake-Review-Report_rev-01.pdf, Rig-Intake-Review-Actions-WE-report.pdf, Synergi-229308-Joint-rig-intake-OMV-Wellesley-DNO-CCB-DSY.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-225623.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-225624.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-226999.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227007.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227012.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227024.pdf, 229227-23-actions-were-captured-during-the-meeting-ref.Follow-up-Actions-.-For-more-information-.pdf, L4-MODU-DSY-E-MA-506-RIG-SPECIFIC-MEASUREMENT-PROGRAM-DSY_2023.pdf, 209017.pdf, 229019-O-1-The-Exercise-and-Training-Report-for-DSY-MOB-FRC.pdf, 229021-Six-6-improvement-suggestions-were-identified-during-the-verification-and-are-described.pdf, 229227-23-actions-were-captured-during-the-meeting-ref.Follow-up-Actions-.-For-more-information-1-1.pdf, L3-MODU-ALL-QU-PR-034-MANAGEMENT-OF-SERVICE-PROVIDERS-ON-MODUS.pdf, L3-MODU-ALL-QU-PR-034-APPENDIX-2-CHECKLIST-VERIFICATION-OF-WORK-SERVICE-PROVIDER.pdf, L3-MODU-ALL-TO-PR-016-TEMPORARY-EQUIPMENT.pdf, L3-MODU-ALL-QU-PR-034-APPENDIX-1.pdf, 228599-DSY-audits-verifications-plan-2023.pdf




New Audit Report

You do not have permission to view this form.


\n


Odfjell Drilling

No person selected

Report No.

5012
Rig Intake Review Report

Type of audit

Rig Intake
Odfjell Drilling

Auditee/Customer

Odfjell Drilling
Wellesley/DNO

Date

2022/12/21

1083 days ago

Findings

40
Number of findings

Status

Closed
Rig Intake


Rig Intake Review Report
Summary

As a part of rig intake and preparations for Wellesley’s and DNO’s exploration wells, Carmen and Norma, an onshore review was held with Odfjell 2nd of December 2022. The review was held at Odfjell’s premises at Kokstadflaten 35 in Bergen.
The review was held in a good atmosphere, the Odfjell participants were very open and willing to explain and share information.
The review team identified two (2) non-conformances, one (1) observation and seven (7) improvement points. The findings are listed in Section 4.
Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.
The review team’s impression is that Odfjell is a rig company that has a well-functioning business management system. Odfjell is ISO 9001 (Quality Management), ISO 14001 (Environmental Management) certified, and the management system is also prepared according to ISO 45001 (Occupational Health and Safety Management) and ISO 50001 (Energy Management). A separate competence review will be scheduled closer to spud on Carmen.

Findings

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    Vaptreat is presented with yellow colour category, but shall be red

    Update Measurement program. Check chemical registration system and update.

    Measurement program is updated with Vaptreat as red colour code. The chemical is also nominated for substitution.

  • Non-Conformity

    Closed


    Closed


    Deadline was:

    L4-MODU-DSY-E-MA-506 Rig specific measurement program is not according to requirements. The description of the chemical treatment system (wrong slop unit etc.) is incorrect.

    Update measurement program

    Synergi 229018
    The masurement program was updated in January 2023 but still som information is missing. – The discharge of BOP fluid not updated to reflect discharges through slop treatment unit (small amounts). The Figure in Ch. 3.1.2 states discharges, but the text still says differently: When it is on deck the BOP fluid can be taken in return through the FRU (Fluid recovery unit) or to slop tank and sent onshore
    – and discharge factor.
    – Additional information should be given regarding usage of Rena unit. Should say that this is a back up system that the client usally have a slop unit onboard.
    – Koper-cote is not included in the program (used on the well head connector, not discharged to sea).
    – Environmental verification 19.-21. april revelaed that the measurement program needs to be updated furter. Some chemicals are missing.

    This action will be followed up in WE Report 5218.

  • Observation

    Closed


    Closed


    Deadline was:

    Insufficient registration/logging of – MOB boat/FRC training. The Exercise and training report are insufficient. The report lacks information on what was done during the training, and it also states the same time for starting and completing of the training.

    The registration/ logging of the training should be according to the training directive.

    19.01.2023 JKAA.  As described, discrepancy between the drill matrix and the actual logged drills/training were observed.  Routines for weekly follow up by SSL is established to ensure that all exercises/training tasks has been met and to ensure quality of logging including the evaluation and corrective actions in case of Performance standar not beeing met.  Routines for exercise follow up by SSL is established in revised CMS ” Verifikasjon og logging av Øvelser i Rig Manager CMS 82051.  And a new Excel file has been made to to cross check training matrix against drills reported in rig manager.  This will make it possible to pinpoint every crewmembers training records for tjhe last 2.5 years

  • Improvement

    Closed


    Closed


    Deadline was:

    Top of helideck skid to be repainted with tiger stripes

    Repaint helideck skid

    Helideck skid has been repainted with tiger stripes. verified during rig inspection 23 January 2023.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider including HPHT competence in competence matrix for drilling personnel

    Ref. synergi 229021

    ANKJ- 04.01.23 We think this is a good suggestion and we will include this in training matrix
    when we have a sollution. We will ask Sven Hope regarding this.
    ÅKP 22.05.23: Still open need to postpone deadline
    ÅKP: 01.08.2023 This i closed in Synergi. The case is with HR and will ble implemented. Case closed

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider providing role familiarization for Safety Delegate

    Have been followed up in synergi 229021

    The safety delegate role will not be included in the familiarization scheme, however there is a VO guideline: L2-NO-HSE-GL-009N that describes the tasks. Spoke to safety delegate from service during Rig visit 23.01.2023. and he said he got a good introduction to the safety delagate role. They have a SD meeting very Fridays and he has 4 hours every week to work with H&S. The HVO has 8 hours every week.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider providing role familiarization for Environmental Officer

    Synergi 229021

    The TSL has been provided training for the role as environmental officer. This is stated in the procedure L3-MODU-ALL-JD-003-017

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider substituting the chemical Vaptreat (red) with SCAL16075A (yellow)

    Vaprtreat is on the substitution list and will be replaced with SCAL16075A during 2023.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider substituting the chemical Jet-Lube HPHT (yellow Y2) with Jet-Lube Seal Guard (yellow)

    20.02.23:
    This product will not be substituted due to technical and security reasons. Manufacturer does not approve that.
    The product will only be used when needed, not regularly.

  • Improvement

    Closed


    Closed


    Deadline was:

    Consider preparing a procedure for handling of drones within 500m zone

    Ref. synergi 229021

    Odfjell has a action plan for management of drones. This is also included in tabletops. Details for reporting is included in Emergency Preparedness bridging document

  • Actions

    Closed


    Closed


    Deadline was:

    Send over presentation from meeting

    Received presentation

  • Actions

    Closed


    Closed


    Deadline was:

    Send updated org. chart for onshore organisation

    Received updated org. charts

  • Actions

    Closed


    Closed


    Deadline was:

    Send an overview of internal deviations registered in synergy

    Received status as pr. 22.20.23

  • Actions

    Closed


    Closed


    Deadline was:

    Inform Bristow on the non-con on 4 cm on helideck

    Bristow informed

  • Actions

    Closed


    Closed


    Deadline was:

    Please provide plans for HMS helideck repeater lights

    Helideck repeater lights are installed and verified during rig visit 23-24 january

  • Actions

    Closed


    Closed


    Deadline was:

    Send QHSE plan and KPI’s

    Synergi 229021

    QHSE Action plan for DSY received

  • Actions

    Closed


    Closed


    Deadline was:

    Send a copy of the Audit Plan for 2023

    Audit plan is received.

  • Actions

    Closed


    Closed


    Deadline was:

    Send Crew rotation plan with legend, explaining the colours

    Received

  • Actions

    Closed


    Closed


    Deadline was:

    Secure proper training on HPHT, and that personnel with HPHT experience are evenly represented in all crews. e.g. crew B

    27.06.2023 Closed

  • Actions

    Closed


    Closed


    Deadline was:

    Send copies of: MODU-ALL-TO-PR-016 Procedure for temporary equipment, L-3-MODU-ALL-QU-PR-034 Procedure for management of service providers on MODU’s, including attachments, The units third party and temporary equipment standard. This is for the operator to forward to service providers.

    synergi 229227

    The documents are received.

  • Actions

    Closed


    Closed


    Deadline was:

    Forward Health and Working environment Plan for 2023

    Received, Synergi 229227

  • Actions

    Closed


    Closed


    Deadline was:

    Invite Åse to AMU meeting in March (and June)

    Åse has received the invitation, but OMV will participate since they have the rig.

  • Actions

    Closed


    Closed


    Deadline was:

    Prepare simulations of oil mist and vapor

    Decided that this is not necessary, personnel will only be exposed for vapour/mist in the shaker room.

  • Actions

    Closed


    Closed


    Deadline was:

    Send a copy of latest Working environment surveys (Noise and Chemical)

    24.06.2023 Received noise report, waiting for chemical
    08.07.2023 Chemical Health Risk Assessment received

  • Actions

    Closed


    Closed


    Deadline was:

    Set a date for a working environment meeting discussing mitigation measures for management of OBM fumes together with occupational health services.

    A working environment meeting has been held, see mom attached

  • Actions

    Closed


    Closed


    Deadline was:

    Secure that temporary equipment is according to Z-015 and S-002 and according to Odfjell requirement

    Information was provided to logistics coordinators for the various service providers.

  • Actions

    Closed


    Closed


    Deadline was:

    SD to be chosen for Crew B from 4S and courses to be schedule

    Closed. Synergi 229227 – Info received 24.03.2023. all crews have a safety delegate

  • Actions

    Closed


    Closed


    Deadline was:

    Odfjell to collect experience from other rigs and purchase screen washer.

    DSN is testing, get information from DSN

    22.05.23 ÅKP Still outstanding, need to postpone deadline
    08.12.2023. • VI har pr i dag en screenwasher men vi undersøker hvilke modeller som er mest egnet et DSY pga brukervennlighet og best egnet plassering i shaker)
    19.02.2024 Followed up in 5968-A10

  • Actions

    Closed


    Closed


    Deadline was:

    Send over a recommendation from Valhall on screen washer

    Sent over recommendation, see attached mail

  • Actions

    Closed


    Closed


    Deadline was:

    Mark power tools with exposure limits

    Synergi 229227. Tools are marked according to procedure

  • Actions

    Closed


    Closed


    Deadline was:

    Send over copy of a report where the FRC from PSV/SBV was lifted to the rig

    Synergi 229227, have revied an overview of exercises. The rig confirms training with the FRC from Siddis Mariner but have not logged the report in Rig manager.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure an overview of f-gases in monthly reports (ref. finding from last verification)

    Synergi 229227. Reveived 23.03.23

  • Actions

    Closed


    Closed


    Deadline was:

    Send over chemical substitution plan for 2023

    Synergi 229227. Reveived 23.03.23

  • Actions

    Closed


    Closed


    Deadline was:

    Send HAZID for pipe handling matrix from 2022

    Received and updated hazid work sheet, but need the report with participants, etc
    17.07.2023 Awaiting New HAZID report, need to postpone deadline.

    Åse: 01.08.2023 Received ny HAZID report. Case closed

  • Actions

    Closed


    Closed


    Deadline was:

    Non-con regarding mooring lines (DNV class 61) – an area on the wires is in poor condition. Mooring line 1,2,5 and 7 to be re-evaluated.

    Mooring lines changed out, DNV is currently approving the documentation (Conditions of class)

  • Actions

    Closed


    Closed


    Deadline was:

    Info/documentation of BOP cutting test of 17” liner/casing

    Synergi 229227
    See DAS for Casing Shear Ram. Cut test are owned by Equinor.
    Operator to decide if testing is to be done and paid for. Or pay Equinor to get access to their report.

  • Actions

    Closed


    Closed


    Deadline was:

    BOP RA incl. LFS5 (one set will arrives 02.02.23, 2 sets 13.04.23). Call for a BOP ram risk assessment

    11.10.23-SS.: BOP Risk Assessment held prior to both Carmen (31.03.23) and Norma (07.06.23). 3 sets of LFS5 are available.

  • Actions

    Closed


    Closed


    Deadline was:

    Answer to Appendix B in PUN report, actions taken
    Copy of 225623.225624, 227024, 227006, 227007, 226999, 227012

    225623 – KPI’s are not measureble
    225624 – Follow up of Environmental aspects and impacts
    226999 – Drillpipes outside bounded area
    227007- Storage of waste in wooden crates
    227012 – Training in detection of spill
    227024 – Signage exiting accommodation
    227006 –

    225623 – KPI’s are now measurable (Closed)
    225624 – Shall be included in the QHSE program and DSY action plans (closed)
    22699 – Area is painted and information posted on a sign (closed)
    227007 –Use IBC (Closed)
    227012 – Since VISSIM is not used onboard at the time Odfjell will postpone this training. OMW is using Safepath and Wellesley, DNO and PUN SmartBlue. (closed)
    227024 – 13.08.22: JKAA Sign on every door leading in/out from changeroom to maindeck is in
    place (closed)
    227006 – Followed up in separate action.

  • Actions

    Closed


    Closed


    Deadline was:

    Present use of lifting coach, scope of work

    Scope is presented to odfjell and the operators. Lifting coach is book out during March.

  • Actions

    Closed


    Closed


    Deadline was:

    Secure coms, radio survey

    Coms secured once on location.



Additional Documentation


Screen-washer.pdf, WE-EA-2022-03-Rig-Intake-Review-Report_rev-01.pdf, Rig-Intake-Review-Actions-WE-report.pdf, Synergi-229308-Joint-rig-intake-OMV-Wellesley-DNO-CCB-DSY.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-225623.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-225624.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-226999.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227007.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227012.pdf, Answer-to-Appendix-B-in-PUN-report-actions-taken-227024.pdf, 229227-23-actions-were-captured-during-the-meeting-ref.Follow-up-Actions-.-For-more-information-.pdf, L4-MODU-DSY-E-MA-506-RIG-SPECIFIC-MEASUREMENT-PROGRAM-DSY_2023.pdf, 209017.pdf, 229019-O-1-The-Exercise-and-Training-Report-for-DSY-MOB-FRC.pdf, 229021-Six-6-improvement-suggestions-were-identified-during-the-verification-and-are-described.pdf, 229227-23-actions-were-captured-during-the-meeting-ref.Follow-up-Actions-.-For-more-information-1-1.pdf, L3-MODU-ALL-QU-PR-034-MANAGEMENT-OF-SERVICE-PROVIDERS-ON-MODUS.pdf, L3-MODU-ALL-QU-PR-034-APPENDIX-2-CHECKLIST-VERIFICATION-OF-WORK-SERVICE-PROVIDER.pdf, L3-MODU-ALL-TO-PR-016-TEMPORARY-EQUIPMENT.pdf, L3-MODU-ALL-QU-PR-034-APPENDIX-1.pdf, 228599-DSY-audits-verifications-plan-2023.pdf



\n”}}]}]}]},{“type”:”section”,”props”:{“class”:”uk-hidden”,”id”:”newreport”,”image_position”:”center-center”,”padding”:”none”,”style”:”default”,”title_breakpoint”:”xl”,”title_position”:”top-left”,”title_rotation”:”left”,”vertical_align”:””,”width”:”default”},”children”:[{“type”:”row”,”children”:[{“type”:”column”,”props”:{“image_position”:”center-center”,”position_sticky_breakpoint”:”m”},”children”:[{“type”:”html”,”props”:{“content”:”

\n

\n

New Audit Report