Odfjell
|
Report No.
|
5892 |
|
Type of audit
|
Rig Intake |
|
Auditee/Customer
|
Odfjell |
|
Date
|
2023/06/05 |
|
Findings
|
18 |
|
Status
|
Closed |
Vår Rig Intake Review meeting report
Summary
The review was held in a good atmosphere, the Odfjell participants were very open and willing to explain and share information.
The review team identified Zero (0) non-conformances, zero (0) observations, one (1) improvement point and 17 actions. The findings are listed in Section 4.
10 Findings from previous rig Intakes are still open and listed in Appendix D.
Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.
The review team’s impression is that Odfjell is a rig company that has a well-functioning business management system. Odfjell is ISO 9001 (Quality Management), ISO 14001 (Environmental Management) certified, and the management system is also prepared according to ISO 45001 (Occupational Health and Safety Management) and ISO 50001 (Energy Management).
Findings
-
IM-1 Odfjell Did not have a procedure for managing Drones on the rig
Prepare procedure for handling of drones within 500m zone. What do one do if the drone lands on the rig?
ÅKP: Recived
-
A-1 Presentation to be sent
Send presentation from meeting
06.06.2023 ÅKP: Presentation received
-
A-2 Replacement of personnel
Inform who Martin Erdal will be replaced by.
24.08.2023 ÅKP: Olsen, Henrik Ramsland have replaced Martin
-
A-3 Synergies to be sent for information
Synergies to be sent:
231851 NC Health control programs
228842 6.2.3 Pipe and riser
231321 DNV CC 6806.06.2023 ÅKP: Synergies received
-
A-4 Overview of HSEQ KPI’s
HSEQ KPI’s for last three years to be sent
24.08.23 ÅKP: Received
-
A-5 Plan for Project : Barrier monitoring
Odfjell to forward plan for organisational and operational barriers to be visualised
20.02.2024 Followed up in 5962-A5
-
A-6 Competence matrix
Show description of colour legend, new on DSY and personnel with less than 3 years’ experience
Send information regarding level 1 and 2 course.ÅKP: Received
-
A-7 Working environment surevys 2022/2023
Send a copy of Working Environment surveys completed in 2022/2023
15.05.2023 ÅP: Received
-
A-8 Temporary equipment
Secure that temporary equipment is according to Z-015 and S-002 and according to Odfjell requirement.
Logistics coordinators from service providers have been informed.
-
A-9 HAVS Procedure
Forward HAVS procedure
ÅKP: Received, but currently being updated
-
A-10 Update of Measurement program
Update measurement program and forward to RIT.
08.12.2023: Received the updated Measurement programme.
29.02.2024: Related to Tomcat AfD we saw that there were wrong information in the programme regarding BOP fluids. The programme was updated immediately and received 29.01.24. -
A-11
Follow up on status on CC’s
Status on CC’s is followed up and the current status is registered in the final Rig Intake Report for Vår Energi.
-
A-12 Anchor wires
Follow up on status on replacement of anchor wires
11.08.2023 ÅKB. Anchor wires have been replaced and update of documentation and class status is ongoing. Will close this when paper work is completed.
29.08.2023 ÅKP Updated Class status report is received and attached. -
A-13 Maintenance on diesel generators
Odfjell to inform RIT on timing for startup of maintenance on diesel generators in due time.
11.10.23: SS – Work in progress. OD has informed us that they are trying out some noise-cancelling curtains that will enable personnel to work in the area over a longer period of time. OD are also currently putting together a plan on how to get this work done without interfering with the operation.
20.02.2023:ÅP – Followed up in 5967-A18 -
A-14 Critical Spare List
Please provide Critical Spares List
Received
-
A-15 Mooring system drawing
Please provide a mooring system drawing with water depth.
11.10.23: SS – A drawing of anchor lines based on depth is provided in the final rig intake report for Vår Energi.
-
A-16
Please provide a copy of synergi 231467.
08.06.2023 ÅKP: Received and forwarded to Helge Nordbø and Helge Vabø
-
A-17 Crane and Lifting verification
Issue a notification letter to Odfjell.
11.10.23:SS- Notification letter was issued to OD 11.09.23.
Additional Documentation
WE-EA-2023-11-Rig-Intake-Review-Report_rev-01_signed.pdf
Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI.pdf
202210-Chemical-Health-Risk-Assessment-Deepsea-Yantai-Oct-22-Final.pdf
Report-Measurments-of-oil-mist-and-oil-vapour-Deepsea-Yantai-February-2023.pdf
Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI-1.pdf
DNV-Survey-Statement-closure-of-condition-of-class-for-mooring-lines-1.pdf
WE-EA-2023-11-Rig-Intake-Review-Report_rev-01_signed.pdf, Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI.pdf, 202210-Chemical-Health-Risk-Assessment-Deepsea-Yantai-Oct-22-Final.pdf, Report-Measurments-of-oil-mist-and-oil-vapour-Deepsea-Yantai-February-2023.pdf, Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI-1.pdf, DSY-Odfjell-skiftplan.xlsx, DNV-Survey-Statement-closure-of-condition-of-class-for-mooring-lines-1.pdf
New Audit Report
\n
Odfjell
|
Report No.
|
5892 |
|
Type of audit
|
Rig Intake |
|
Auditee/Customer
|
Odfjell |
|
Date
|
2023/06/05 |
|
Findings
|
18 |
|
Status
|
Closed |
Vår Rig Intake Review meeting report
Summary
The review was held in a good atmosphere, the Odfjell participants were very open and willing to explain and share information.
The review team identified Zero (0) non-conformances, zero (0) observations, one (1) improvement point and 17 actions. The findings are listed in Section 4.
10 Findings from previous rig Intakes are still open and listed in Appendix D.
Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.
The review team’s impression is that Odfjell is a rig company that has a well-functioning business management system. Odfjell is ISO 9001 (Quality Management), ISO 14001 (Environmental Management) certified, and the management system is also prepared according to ISO 45001 (Occupational Health and Safety Management) and ISO 50001 (Energy Management).
Findings
-
IM-1 Odfjell Did not have a procedure for managing Drones on the rig
Prepare procedure for handling of drones within 500m zone. What do one do if the drone lands on the rig?
ÅKP: Recived
-
A-1 Presentation to be sent
Send presentation from meeting
06.06.2023 ÅKP: Presentation received
-
A-2 Replacement of personnel
Inform who Martin Erdal will be replaced by.
24.08.2023 ÅKP: Olsen, Henrik Ramsland have replaced Martin
-
A-3 Synergies to be sent for information
Synergies to be sent:
231851 NC Health control programs
228842 6.2.3 Pipe and riser
231321 DNV CC 6806.06.2023 ÅKP: Synergies received
-
A-4 Overview of HSEQ KPI’s
HSEQ KPI’s for last three years to be sent
24.08.23 ÅKP: Received
-
A-5 Plan for Project : Barrier monitoring
Odfjell to forward plan for organisational and operational barriers to be visualised
20.02.2024 Followed up in 5962-A5
-
A-6 Competence matrix
Show description of colour legend, new on DSY and personnel with less than 3 years’ experience
Send information regarding level 1 and 2 course.ÅKP: Received
-
A-7 Working environment surevys 2022/2023
Send a copy of Working Environment surveys completed in 2022/2023
15.05.2023 ÅP: Received
-
A-8 Temporary equipment
Secure that temporary equipment is according to Z-015 and S-002 and according to Odfjell requirement.
Logistics coordinators from service providers have been informed.
-
A-9 HAVS Procedure
Forward HAVS procedure
ÅKP: Received, but currently being updated
-
A-10 Update of Measurement program
Update measurement program and forward to RIT.
08.12.2023: Received the updated Measurement programme.
29.02.2024: Related to Tomcat AfD we saw that there were wrong information in the programme regarding BOP fluids. The programme was updated immediately and received 29.01.24. -
A-11
Follow up on status on CC’s
Status on CC’s is followed up and the current status is registered in the final Rig Intake Report for Vår Energi.
-
A-12 Anchor wires
Follow up on status on replacement of anchor wires
11.08.2023 ÅKB. Anchor wires have been replaced and update of documentation and class status is ongoing. Will close this when paper work is completed.
29.08.2023 ÅKP Updated Class status report is received and attached. -
A-13 Maintenance on diesel generators
Odfjell to inform RIT on timing for startup of maintenance on diesel generators in due time.
11.10.23: SS – Work in progress. OD has informed us that they are trying out some noise-cancelling curtains that will enable personnel to work in the area over a longer period of time. OD are also currently putting together a plan on how to get this work done without interfering with the operation.
20.02.2023:ÅP – Followed up in 5967-A18 -
A-14 Critical Spare List
Please provide Critical Spares List
Received
-
A-15 Mooring system drawing
Please provide a mooring system drawing with water depth.
11.10.23: SS – A drawing of anchor lines based on depth is provided in the final rig intake report for Vår Energi.
-
A-16
Please provide a copy of synergi 231467.
08.06.2023 ÅKP: Received and forwarded to Helge Nordbø and Helge Vabø
-
A-17 Crane and Lifting verification
Issue a notification letter to Odfjell.
11.10.23:SS- Notification letter was issued to OD 11.09.23.
Additional Documentation
WE-EA-2023-11-Rig-Intake-Review-Report_rev-01_signed.pdf
Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI.pdf
202210-Chemical-Health-Risk-Assessment-Deepsea-Yantai-Oct-22-Final.pdf
Report-Measurments-of-oil-mist-and-oil-vapour-Deepsea-Yantai-February-2023.pdf
Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI-1.pdf
DNV-Survey-Statement-closure-of-condition-of-class-for-mooring-lines-1.pdf
WE-EA-2023-11-Rig-Intake-Review-Report_rev-01_signed.pdf, Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI.pdf, 202210-Chemical-Health-Risk-Assessment-Deepsea-Yantai-Oct-22-Final.pdf, Report-Measurments-of-oil-mist-and-oil-vapour-Deepsea-Yantai-February-2023.pdf, Synergi-231960.-Var-RIG-INTAKE-REVIEW-FOR-THE-RINGHORNE-NORTHAND-HUBERT-MAGELAN-DRILLING-OPERATI-1.pdf, DSY-Odfjell-skiftplan.xlsx, DNV-Survey-Statement-closure-of-condition-of-class-for-mooring-lines-1.pdf