Noble Drilling AS

|
Report No.
|
6334 |
|
Type of audit
|
Rig Intake |
|
Auditee/Customer
|
Noble Drilling AS |
|
Date
|
2024/02/22 |
|
Findings
|
68 |
|
Status
|
Registered |
Falstaff Onshore Verification
Summary
The verification was held at Noble’s premises at Moseidveien 19, in Stavanger, 22-23rd of February.
The verification meetings were held in a good atmosphere, the Noble participants were very open and willing to explain and share information.
The verification team identified zero (0) non-conformance, zero (0) observations, seven (7) improvement suggestions and 57 actions. None of the findings are considered critical for operation. The findings are listed in Section 4.1-4.4.
Noble is requested to respond within two weeks of receiving this report on how they intended to handle the findings and sending Wellesley the required information.
The verification team’s impression is that Noble is a rig company that has a well-functioning business management system. Noble does not have certification according to ISO 9001, 14001, ISO 45001 and 50014.
A separate competence review meeting will be scheduled closer to spud.
Findings
-
Look into a way of better securing stored equipment at height in sack store racks
OIM has conducted inspection in relevant area. Conclusion is that no additional securing will be put in place. In preparation for rig move necessary precautions are taken, and the Tow Master and Warranty Surveyor do an inspection on the rig.
-
Handling of loose lifting equipment. Ensure that returned equipment are not being re-used without being properly checked in
Hatch will be made for delivery of slings into the locked area of the sling store before startup Falstaff.
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 9001: Quality Management – ensure to comply with section 4.4.1 “maintain” and “improve” and 7.5.3.2 (c) “control of changes (e.g. version control)”Bridging document is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 14001: Environmental Management SystemsBridging document is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 27001: Cyber SecurityReview ongoing. Plan to do a NIST CSF maturity assessment during the summer
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 45001: Occupational Health and Safety. This is also requested in Magnet JQSGap analysis is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 50001: Energy ManagementEnergy management plan is under development for INV. Update June. Still not completed.
We are aiming to have it done before startup on Falstaff. -
DNO recommend to implement revision number on the Measurement program
– Noble Invincible Measurement program does not have a document number or a revision tracker.
– This is by Noble seen as an Outcome document. But this document does not have anything to measure against.
– This document gives an overview over rig chemicals, diesel, slips, bilge, etc, usage and discharge and the uncertainties in the measurements. This is used as a basis for the operators as input for discharges applications.Plan to issue a new document revision, with revision number, and revision history in the document
24.7 Env measurement program – Sent and done. Document uploaded to folder – see document 17.
-
DNO recommend to start register underlying cause and potential consequences (level 1-2).
It is difficult to do trending, without this inputPlan to update Event reporting solution with a new module with Cause description. Description of Incident Potential is already in place
This will be implemented in Noble’s incident reporting. Estimated Q3.
-
DNO recommend to implement notice when deadlines for actions are approaching
To secure that all open actions are closed within the given time frame24.7 Reminders when RCAL actions are due are now given. The person assigned to the action and the person who created the RCAL receive a notification 15 days before it expires. A notification is also given when the action is overdue
-
DNO recommend to update the CORA to reflect actual work the rig is performing and the areas it is operating
– Noble Invincible’s CORA is not updated since 2014. It is assumed that several assumptions in this risk assessment have changed
– i.e. the traffic in the Frigg area and near Ekofisk could have changed the last 10 yearsNoble will issue an assessment of Drilling Program Assumptions for Noble Invincible in CORA vs. 2024 Drilling program.
4.7.24 Uploaded email to DNO / Well Expertise as document 7 in “recommendations”.
-
Noble to provide status on multi machine upgrade including training and commissioning checks
Training for crews will commence in May. Installation is planned for July. Plan for installation is uploaded to sharepoint
Update 4.7.24
1. MMC:
a. According to Operations progress mobilization of NOV/Paal Hansen (Noble ET in charge of installation) is planned for 10/8/2024. Will be adjusted when we get closer to end of HOD-A operations,
b. Most recent Project Plan attached ( starting date is 15th for calculation purposes only, will be adjusted). See document 1 in the technical folder.
c. Training: we did first session for Crew anyhow provided training was not in accordance with Noble expectations, presently there is ongoing communication between Noble and NOV on finding way forward.
d. Paal Hansen (Noble ET working on installation) is due to join simulator test in week 32 ( 5-8/08/2024) , monitoring due date.
e. NOV is working to prepare video showing features of MMC 3.5. Will be shared with DNO/ Well expertise if of interest. -
Noble to provide ETA for BOP critical spares and mitigating plans
Majority of spare parts have already been delivered to PSW. Awaiting update on a few remaining parts. Update will be shared when information is received
-
Noble to perform cold cutter checks with tension ring (interface verification and dimension check)
Action assigned to Onshore Rig Planner (Noble)
-
Noble to provide status on hydrocarbon bearing hoses prior to startup. Evaluate to replace hoses in due time
Status provided to Stig Seland 23.2 Email is uploaded to folder
-
Provide the plan on replacing the watertight doors
Status 4.7.24
Cantilever doors:
a. NOS mobilized on 26th of June, 2 mechanics.
b. Total 8 doors to be replaced: as per today replaced 2 doors, third one is in progress
c. See saved door list (document 5 in technical folder) : Replaced doors C003-2 and C103-2 , replacement in shale shakers ongoing -
Noble to provide transfer procedures
Uploaded to Sharepoint folder
-
Provide “Close out letter” to Havindustritilsynet (Havtil) to DNO
Uploaded to Sharepoint folder
-
Noble to provide result from ESD test including Lesson Learned if any
Uploaded to Sharepoint folder
-
Noble to present a plan on when the hooking up of motion sensors to the helideck
Equipment has been ordered. Installation planned for June 24
-
Provide status update on the complete replacement of the the BluNox unit on DG #3 exhaust system
Uploaded to Sharepoint folder
-
Clarify / checking plan for heavy lift (“hammer”), high number of container lifts (DNO)
-
Noble to provide copy of helideck certificate
Uploaded to Sharepoint folder
-
Noble to provide copy of helideck certificate
Uploaded to Sharepoint folder
-
Noble to provide evidence of Helifuel system in operation/ recertified OK
Service personnel planned out 3rd April for inspection. Certificate will be uploaded afterwards
Uploaded to folder. See document 13
-
Evaluate need for lifting coach (DNO & Noble)
Current status – not planned.
-
DNO to set up a separate risk assessment with regards to Hammer. Include anti-collision, lifting procedures and weight limitations on catwalk etc. (DNO)
Risk assessment held on 10th of April
-
Provide result from DROPS inspection
No third party drops inspection planned before Falstaff.
Most recent inspection by Westcon:
“One outstanding action. Correction ongoing. See copy of WO in document 28” -
Provide relevant Certificate of Compliance certificates prior to startup on Falstaff
Status 4.7.24
CoC:
a. See attached recently implemented Noble COSC Program (document 17 in technical folder)
b. The new NOV program is a COSC (Certificate of Service Continuous) issuance and renewal program and is only applicable to the enrolled equipment which is limited to the Drill Floor (DWWKS, Top Drives, Crown Blocks (Cluster), Travelling Blocks).
c. Status for Invincible:
Completed:
i. G3103-Z-VA-065 Rev. 04 – Top Drive, S/N: G3103-4213 ( attached – document 17 a)
ii. G3104-Z-VA-065 Rev. 04 – Top Drive, S/N: G3104-4213 ( attached document 17 b)
S01L4373-Z-VA-065 – (Main) Drawworks, S01L4373-672Pending:
iii. L4302-Z-VA-065 – CBC, S/N: L4302-0115
iv. S01L4373-Z-VA-065 – (Main) Drawworks, S01L4373-672Presently we are collecting final data for last two items, last CoSC shall be issued by end of July.
-
Noble to provide more updated HP Mud system pressure relief certificates.
Update 4.7.24
Titan Valves:
a. We had Trescal for verification of HP Relief valves anyhow they were not able to any certification on site,
b. Decided to purchase 1 pce of Titan valve from Interceptor, PO 300000040
c. Ordered pce is on Rig and will be replaced in next days,
d. Once replaced we will send our valve for calibration and testing onshore, then will continue with next one same way.
Process of testing and replacing the valves will be ongoing on the rig during Falstaff -
DNO to set up a separate risk assessment with regards to cuttings handling (DNO)
Risk assessment held on 13.5
-
Noble to provide pit diagram
Uploaded to Sharepoint folder
-
Noble to share shear matrix when available
21.8 Documentation shared with DNO by rig planner. Uploaded to SP folder.
-
Noble to share closeout notes from AkerBp well control audit once performed
Actions being addressed in IFS audit case.
-
Noble to provide 3rd party inspection on Well Control by AkerBP when available
Document received is uploaded to SP folder. See document 23. Audit case 2761 created in IFS to address findings.
– 4 Observations in total. -
DNO to look into real-time system with regards to IT and firewalls (DNO & Noble)
IT dialogue ongoing between Noble, AkerBP and DNO
-
DNO IT department to evaluate solutions regarding integrating, i.e. DNO Offshore Geo operations
(DNO & Noble) -
DNO to set up a conductor handling risk assessment. Need to update pipe handling matrix? (DNO)
RA Performed 10th April.
-
Noble to present an assessment or statement with regards to the Havtil study related to Hydrogen assisted cracking
Uploaded to Sharepoint folder.
Uploaded. Note, content is confidential and should not be shared. See document 27 on SP folder
-
Noble to provide picture book
Uploaded to Sharepoint folder
-
Provide status list of AoC both short and long list and copy of letters
Uploaded to Sharepoint folder
-
Provide a list of Internal deviations
15.7 Uploaded. See document 2 in HSE folder.
-
Arrange meeting with presentation of the Management system, to improve understanding of the Noble Management system
Presentation held 11th of March
-
Provide Document Management procedure
Uploaded to Sharepoint folder, for P2R
-
Provide a template for the Bi-weekly HSE meeting
Uploaded to HSE folder. See document 4.
-
Provide an example of Barrier management topic
7.8 OIM replied to email regarding this topic on the 2nd of July. Email uploaded to folder.
-
Provide results of Hazard Identification (HAZID) and Bowtie review workshop with crew and rig team members
3.7 Excel sheet uploaded to folder. See document 7 in HSE folder.
-
Provide Status Havtil 2020 and 2023 audit report
Uploaded to folder. See folder numbered 8. Regarding HAVTIL 23 report – see also excel sheet that shows update from early June.
-
Provide External audits and verifications plan for 2024
Uploaded to Sharepoint folder
-
Competence review meeting to be scheduled 1 month before spud (DNO)
21.8 Competence review carried out.
-
Provide Noise- / Product datasheet from the supplier of the Conductor “hammer”. (DNO)
-
Provide Temporary equipment procedure and check list (ref. NORSOK S-002)
Uploaded to Sharepoint folder
-
Evaluate the solution for Falstaff participation in Noble Invincible WEC DNO & Noble
Next WEC planned for 18.9 DNO will be invited. Suggest to keep HAL WEC representative as today for service.
-
Provide copies of the previous two WEC MoMs
Uploaded to folder – see documents 14 (2)
-
Provide a copy of the yearly WEC report 2023
Unfortunately not made for 2023. Not available. Will be made for 2024.
-
Review Environmental Aspects prior to Falstaff
(DNO & Noble)7.8 Conclusion based on updated procecdure is that it is not required to update environmental aspects based on change of client. Operations that will be done at Falstaff will include the same broad operations categories of activities as any exploration well. Email sent to Sanne about topic as well.
-
Provide External Environment Verification Report (Aker BP)
Uploaded to Sharepoint folder
-
Generalize measurement program to fit more than Aker BP
15.7 Updated version is uploaded.
-
Send 3rd party SDS to medic. Inform Noble if chemicals with high risk are planned to be used (DNO)
Information regarding chemicals register sent to DNO by HSE Barbara to register chemicals before start of operation.
-
Update Chemical Management procedure (EcoOnline – Aker BP mentioned)
4.7.24 Procedure updated. See document 20 in the HSE folder.
-
Provide Ozone depleting and Greenhouse gasses procedure
Uploaded to Sharepoint folder
-
Generalize Waste management plan (WMP) For Falstaff use
24.7 See document 22 uploaded to folder.
-
Provide access to Power BI – for Fuel consumption, from start-up of Falstaff operations
Access given to Anniken and Helene.
-
Send status on KPI for energy management
See email regarding topic – document 24
-
Provide information about targets for Environmental, Social and Governance (ESG) KPIs
Noble Sustainability department inform that there are no specific social or governance targets for 24, except those focus areas that are described in the 23 sustainability report.
-
Share Monthly Man hour report
Uploaded to Sharepoint folder
-
Provide DROPS (Dropped Objects Prevention Scheme) manual for Noble Invincible
Uploaded to Sharepoint folder
-
Provide status on DROPS inspection from Westcon
Awaiting feedback from offshore team
One outstanding action. Correction ongoing. See copy of WO in document 28
Additional Documentation
PL1086-DNO-D-RA-0011-Falstaff-Onshore-Rig-Intake-Verification-Report-rev.02-signert.pdf
New Audit Report
\n
Noble Drilling AS

|
Report No.
|
6334 |
|
Type of audit
|
Rig Intake |
|
Auditee/Customer
|
Noble Drilling AS |
|
Date
|
2024/02/22 |
|
Findings
|
68 |
|
Status
|
Registered |
Falstaff Onshore Verification
Summary
The verification was held at Noble’s premises at Moseidveien 19, in Stavanger, 22-23rd of February.
The verification meetings were held in a good atmosphere, the Noble participants were very open and willing to explain and share information.
The verification team identified zero (0) non-conformance, zero (0) observations, seven (7) improvement suggestions and 57 actions. None of the findings are considered critical for operation. The findings are listed in Section 4.1-4.4.
Noble is requested to respond within two weeks of receiving this report on how they intended to handle the findings and sending Wellesley the required information.
The verification team’s impression is that Noble is a rig company that has a well-functioning business management system. Noble does not have certification according to ISO 9001, 14001, ISO 45001 and 50014.
A separate competence review meeting will be scheduled closer to spud.
Findings
-
Look into a way of better securing stored equipment at height in sack store racks
OIM has conducted inspection in relevant area. Conclusion is that no additional securing will be put in place. In preparation for rig move necessary precautions are taken, and the Tow Master and Warranty Surveyor do an inspection on the rig.
-
Handling of loose lifting equipment. Ensure that returned equipment are not being re-used without being properly checked in
Hatch will be made for delivery of slings into the locked area of the sling store before startup Falstaff.
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 9001: Quality Management – ensure to comply with section 4.4.1 “maintain” and “improve” and 7.5.3.2 (c) “control of changes (e.g. version control)”Bridging document is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 14001: Environmental Management SystemsBridging document is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 27001: Cyber SecurityReview ongoing. Plan to do a NIST CSF maturity assessment during the summer
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 45001: Occupational Health and Safety. This is also requested in Magnet JQSGap analysis is issued, uploaded to sharepoint
-
Noble state that they are complying to the ISO standards 9001, 14001, 45001 and 50001.
DNO recommend Noble to perform GAP analysis’ for:
– ISO 50001: Energy ManagementEnergy management plan is under development for INV. Update June. Still not completed.
We are aiming to have it done before startup on Falstaff. -
DNO recommend to implement revision number on the Measurement program
– Noble Invincible Measurement program does not have a document number or a revision tracker.
– This is by Noble seen as an Outcome document. But this document does not have anything to measure against.
– This document gives an overview over rig chemicals, diesel, slips, bilge, etc, usage and discharge and the uncertainties in the measurements. This is used as a basis for the operators as input for discharges applications.Plan to issue a new document revision, with revision number, and revision history in the document
24.7 Env measurement program – Sent and done. Document uploaded to folder – see document 17.
-
DNO recommend to start register underlying cause and potential consequences (level 1-2).
It is difficult to do trending, without this inputPlan to update Event reporting solution with a new module with Cause description. Description of Incident Potential is already in place
This will be implemented in Noble’s incident reporting. Estimated Q3.
-
DNO recommend to implement notice when deadlines for actions are approaching
To secure that all open actions are closed within the given time frame24.7 Reminders when RCAL actions are due are now given. The person assigned to the action and the person who created the RCAL receive a notification 15 days before it expires. A notification is also given when the action is overdue
-
DNO recommend to update the CORA to reflect actual work the rig is performing and the areas it is operating
– Noble Invincible’s CORA is not updated since 2014. It is assumed that several assumptions in this risk assessment have changed
– i.e. the traffic in the Frigg area and near Ekofisk could have changed the last 10 yearsNoble will issue an assessment of Drilling Program Assumptions for Noble Invincible in CORA vs. 2024 Drilling program.
4.7.24 Uploaded email to DNO / Well Expertise as document 7 in “recommendations”.
-
Noble to provide status on multi machine upgrade including training and commissioning checks
Training for crews will commence in May. Installation is planned for July. Plan for installation is uploaded to sharepoint
Update 4.7.24
1. MMC:
a. According to Operations progress mobilization of NOV/Paal Hansen (Noble ET in charge of installation) is planned for 10/8/2024. Will be adjusted when we get closer to end of HOD-A operations,
b. Most recent Project Plan attached ( starting date is 15th for calculation purposes only, will be adjusted). See document 1 in the technical folder.
c. Training: we did first session for Crew anyhow provided training was not in accordance with Noble expectations, presently there is ongoing communication between Noble and NOV on finding way forward.
d. Paal Hansen (Noble ET working on installation) is due to join simulator test in week 32 ( 5-8/08/2024) , monitoring due date.
e. NOV is working to prepare video showing features of MMC 3.5. Will be shared with DNO/ Well expertise if of interest. -
Noble to provide ETA for BOP critical spares and mitigating plans
Majority of spare parts have already been delivered to PSW. Awaiting update on a few remaining parts. Update will be shared when information is received
-
Noble to perform cold cutter checks with tension ring (interface verification and dimension check)
Action assigned to Onshore Rig Planner (Noble)
-
Noble to provide status on hydrocarbon bearing hoses prior to startup. Evaluate to replace hoses in due time
Status provided to Stig Seland 23.2 Email is uploaded to folder
-
Provide the plan on replacing the watertight doors
Status 4.7.24
Cantilever doors:
a. NOS mobilized on 26th of June, 2 mechanics.
b. Total 8 doors to be replaced: as per today replaced 2 doors, third one is in progress
c. See saved door list (document 5 in technical folder) : Replaced doors C003-2 and C103-2 , replacement in shale shakers ongoing -
Noble to provide transfer procedures
Uploaded to Sharepoint folder
-
Provide “Close out letter” to Havindustritilsynet (Havtil) to DNO
Uploaded to Sharepoint folder
-
Noble to provide result from ESD test including Lesson Learned if any
Uploaded to Sharepoint folder
-
Noble to present a plan on when the hooking up of motion sensors to the helideck
Equipment has been ordered. Installation planned for June 24
-
Provide status update on the complete replacement of the the BluNox unit on DG #3 exhaust system
Uploaded to Sharepoint folder
-
Clarify / checking plan for heavy lift (“hammer”), high number of container lifts (DNO)
-
Noble to provide copy of helideck certificate
Uploaded to Sharepoint folder
-
Noble to provide copy of helideck certificate
Uploaded to Sharepoint folder
-
Noble to provide evidence of Helifuel system in operation/ recertified OK
Service personnel planned out 3rd April for inspection. Certificate will be uploaded afterwards
Uploaded to folder. See document 13
-
Evaluate need for lifting coach (DNO & Noble)
Current status – not planned.
-
DNO to set up a separate risk assessment with regards to Hammer. Include anti-collision, lifting procedures and weight limitations on catwalk etc. (DNO)
Risk assessment held on 10th of April
-
Provide result from DROPS inspection
No third party drops inspection planned before Falstaff.
Most recent inspection by Westcon:
“One outstanding action. Correction ongoing. See copy of WO in document 28” -
Provide relevant Certificate of Compliance certificates prior to startup on Falstaff
Status 4.7.24
CoC:
a. See attached recently implemented Noble COSC Program (document 17 in technical folder)
b. The new NOV program is a COSC (Certificate of Service Continuous) issuance and renewal program and is only applicable to the enrolled equipment which is limited to the Drill Floor (DWWKS, Top Drives, Crown Blocks (Cluster), Travelling Blocks).
c. Status for Invincible:
Completed:
i. G3103-Z-VA-065 Rev. 04 – Top Drive, S/N: G3103-4213 ( attached – document 17 a)
ii. G3104-Z-VA-065 Rev. 04 – Top Drive, S/N: G3104-4213 ( attached document 17 b)
S01L4373-Z-VA-065 – (Main) Drawworks, S01L4373-672Pending:
iii. L4302-Z-VA-065 – CBC, S/N: L4302-0115
iv. S01L4373-Z-VA-065 – (Main) Drawworks, S01L4373-672Presently we are collecting final data for last two items, last CoSC shall be issued by end of July.
-
Noble to provide more updated HP Mud system pressure relief certificates.
Update 4.7.24
Titan Valves:
a. We had Trescal for verification of HP Relief valves anyhow they were not able to any certification on site,
b. Decided to purchase 1 pce of Titan valve from Interceptor, PO 300000040
c. Ordered pce is on Rig and will be replaced in next days,
d. Once replaced we will send our valve for calibration and testing onshore, then will continue with next one same way.
Process of testing and replacing the valves will be ongoing on the rig during Falstaff -
DNO to set up a separate risk assessment with regards to cuttings handling (DNO)
Risk assessment held on 13.5
-
Noble to provide pit diagram
Uploaded to Sharepoint folder
-
Noble to share shear matrix when available
21.8 Documentation shared with DNO by rig planner. Uploaded to SP folder.
-
Noble to share closeout notes from AkerBp well control audit once performed
Actions being addressed in IFS audit case.
-
Noble to provide 3rd party inspection on Well Control by AkerBP when available
Document received is uploaded to SP folder. See document 23. Audit case 2761 created in IFS to address findings.
– 4 Observations in total. -
DNO to look into real-time system with regards to IT and firewalls (DNO & Noble)
IT dialogue ongoing between Noble, AkerBP and DNO
-
DNO IT department to evaluate solutions regarding integrating, i.e. DNO Offshore Geo operations
(DNO & Noble) -
DNO to set up a conductor handling risk assessment. Need to update pipe handling matrix? (DNO)
RA Performed 10th April.
-
Noble to present an assessment or statement with regards to the Havtil study related to Hydrogen assisted cracking
Uploaded to Sharepoint folder.
Uploaded. Note, content is confidential and should not be shared. See document 27 on SP folder
-
Noble to provide picture book
Uploaded to Sharepoint folder
-
Provide status list of AoC both short and long list and copy of letters
Uploaded to Sharepoint folder
-
Provide a list of Internal deviations
15.7 Uploaded. See document 2 in HSE folder.
-
Arrange meeting with presentation of the Management system, to improve understanding of the Noble Management system
Presentation held 11th of March
-
Provide Document Management procedure
Uploaded to Sharepoint folder, for P2R
-
Provide a template for the Bi-weekly HSE meeting
Uploaded to HSE folder. See document 4.
-
Provide an example of Barrier management topic
7.8 OIM replied to email regarding this topic on the 2nd of July. Email uploaded to folder.
-
Provide results of Hazard Identification (HAZID) and Bowtie review workshop with crew and rig team members
3.7 Excel sheet uploaded to folder. See document 7 in HSE folder.
-
Provide Status Havtil 2020 and 2023 audit report
Uploaded to folder. See folder numbered 8. Regarding HAVTIL 23 report – see also excel sheet that shows update from early June.
-
Provide External audits and verifications plan for 2024
Uploaded to Sharepoint folder
-
Competence review meeting to be scheduled 1 month before spud (DNO)
21.8 Competence review carried out.
-
Provide Noise- / Product datasheet from the supplier of the Conductor “hammer”. (DNO)
-
Provide Temporary equipment procedure and check list (ref. NORSOK S-002)
Uploaded to Sharepoint folder
-
Evaluate the solution for Falstaff participation in Noble Invincible WEC DNO & Noble
Next WEC planned for 18.9 DNO will be invited. Suggest to keep HAL WEC representative as today for service.
-
Provide copies of the previous two WEC MoMs
Uploaded to folder – see documents 14 (2)
-
Provide a copy of the yearly WEC report 2023
Unfortunately not made for 2023. Not available. Will be made for 2024.
-
Review Environmental Aspects prior to Falstaff
(DNO & Noble)7.8 Conclusion based on updated procecdure is that it is not required to update environmental aspects based on change of client. Operations that will be done at Falstaff will include the same broad operations categories of activities as any exploration well. Email sent to Sanne about topic as well.
-
Provide External Environment Verification Report (Aker BP)
Uploaded to Sharepoint folder
-
Generalize measurement program to fit more than Aker BP
15.7 Updated version is uploaded.
-
Send 3rd party SDS to medic. Inform Noble if chemicals with high risk are planned to be used (DNO)
Information regarding chemicals register sent to DNO by HSE Barbara to register chemicals before start of operation.
-
Update Chemical Management procedure (EcoOnline – Aker BP mentioned)
4.7.24 Procedure updated. See document 20 in the HSE folder.
-
Provide Ozone depleting and Greenhouse gasses procedure
Uploaded to Sharepoint folder
-
Generalize Waste management plan (WMP) For Falstaff use
24.7 See document 22 uploaded to folder.
-
Provide access to Power BI – for Fuel consumption, from start-up of Falstaff operations
Access given to Anniken and Helene.
-
Send status on KPI for energy management
See email regarding topic – document 24
-
Provide information about targets for Environmental, Social and Governance (ESG) KPIs
Noble Sustainability department inform that there are no specific social or governance targets for 24, except those focus areas that are described in the 23 sustainability report.
-
Share Monthly Man hour report
Uploaded to Sharepoint folder
-
Provide DROPS (Dropped Objects Prevention Scheme) manual for Noble Invincible
Uploaded to Sharepoint folder
-
Provide status on DROPS inspection from Westcon
Awaiting feedback from offshore team
One outstanding action. Correction ongoing. See copy of WO in document 28
Additional Documentation
PL1086-DNO-D-RA-0011-Falstaff-Onshore-Rig-Intake-Verification-Report-rev.02-signert.pdf