WE Report

Audits



Odfjell

No person selected

Report No.

6879
Joint Rig Inspection – DSY

Type of audit

Rig Intake
Odfjell

Auditee/Customer

Odfjell
Orlen Upstream Norway & DNO Norge

Date

2024/11/06

396 days ago

Findings

23
Number of findings

Status

Closed
Rig Intake


Joint Rig Inspection – DSY
Summary

As part of rig intake and preparations for PUN’s and DNO’s exploration wells, Tomcat and Kjøttkake, a rig inspection was carried out when the rig was at on contract with Shell on Knarr.
The Rig Intake Team (RIT) would like to acknowledge the support provided by Odfjell and service personnel during the verification. All persons involved from Odfjell and Service Companies were open, extremely
helpful and positive.

The overall impression is that the rig is effectively managed by Odfjell, rig equipment is in uniformly good condition and housekeeping is maintained at a very high standard.

The inspection team identified 23 findings, zero (0) non-conformances, two (2) observation and twentyone (21) improvement points. The findings are listed in chapter 4.

Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.

Findings

  • Observation

    Closed


    Closed


    Deadline was:

    Rig Inspection – O-1
    “Broken guard on pillar drill” – The guard on the rotating drill chuck on the pillar drill in the welder’s shop was broken.

    Replace ASAP.

    11.11.24 KNB: Dette er utbedret nå.

  • Observation

    Closed


    Closed


    Deadline was:

    Rig Inspection – O-2
    “Liner covers” – Covers observed to be raised up. Covers to be retained closed during operation.

    Covers to be retained closed during operation

    OD frist: 01.02.2025

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-1:
    “Labeling of handheld tools” – The tools were not labelled according to SfS recommendation 044N Labelling and use of handheld tools. The guideline was published in 2021.

    More resources should be available to get this in place.

    12.11.24 KWIR We have an ongoing project of marking HAVS Tools

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Safety Officer

    21.11.24: EKE. We have received new lists from ISOS. The lists are posted on the tool cabinet for the deck crew, mechanics, welders cabinet. We have also labelled the tools with stickers showing category of tool.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-3:
    “Simulator training for medics” – When the duty doctor arrangement is sentralised it is required to have telemedecine connected to the duty doctor an the Medics shall be trainied in the emergeny medical treatment protocols (Simulator Training)

    Schedule Simulator training for medics

    Dette er et krav og må være på plass før DNO / kjøttkake Offshore norge sitt krav 014

    Tiltaksansvarlig bruker: Snekkevik Odd-Egil (DSY Rig Manager)

    Info from Odfjell: Supplier of course is Prometheus (previous Safeguard)
    Two days course: Live tissue / Simulator training.
    Scheduled Week 44 and 48 – 2024

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-4:
    “NDT inspection of loose drilling equipment” – All this equipment was last inspected August 2023. Now due for reinspection.

    Odfjell to schedule reinspection ASAP.

    12.11.24 Bjbe Axxes performed inspection april 2024

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-5:
    “Rig blackout test” – Odfjell to report back when reasons for deadship generator failing to start during blackout test have been established

    Send investigation report or result from new test to RIL

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Andersen Kenneth Holm

    Repaired

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-6:
    “Upcoming SPS” – The SPS workscope is run by a dedicated shoreside based team commissioning and reviewing equipment condition assessments then mobilising mechanics, electricians, vendor representatives eg NOV, NDT specialists etc to visit the rig. A substantial amount of SPS work appears to have been completed ahead of the yard stay.

    Please provide an overview of Scope of Work required for the SPS Quayside period towards the end of the Shell PPP&A campaign.
    Please also provide a Scope of Work for any campaign of “rig maintenance catch-up” to be performed during the SPS Quayside period.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Andersen Kenneth Holm

    SPS is complete. OD has high focus on bringing the maintenance numbers down. This is followed up during the

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-7:
    “Wire lubrication” – Some of the crane wire looked dry.

    Recommend that lubrication routines are reviewed to ascertain if more lubrication required.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-8:
    “Air conditioning, operator’s cabin, starboard crane” – A/C unit was out of order in starboard crane.

    Please report when replaced and temporary fan removed from crane operator’s cabin

    Tiltaksansvarlig bruker: DSY Technical Section Leader

    12.11.2024 RBR: A/C unit replaced

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-9:
    “Machinery room work bench, starboard crane” – House keeping could be improved and the bench tidied up.

    Improve housekeeping in machine room, starboard crane

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-10:
    “Fire fighting provision in crane” – Improvement Suggestion from previous inspection which is still valid: the crane machinery room has a large inventory of hydraulic oil. In the event of a leak in the hydraulic system this oil can be released under pressure and vaporised. Depending on the oil type, this could represent a fire hazard if ignited. A single portable fire extinguisher may not be adequate for a fire in the crane machinery room. It is suggested that this is evaluated further.

    Evaluate further requirements for firefighting equipment in crane machinery room.

    15.01.2025 Evaluation is that there is no need for additional fire extinguisher

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-11:
    “Hydraracker maintenance” – From last inspection but still valid: The Hydraracker does not have redundancy, failure of it during service would result in downtime. Given the criticality and lack of redundancy of the Hydraracker.

    Please perform a detailed review of Hydraracker maintenance condition.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Technical Section Leader

    18.12.24 Hoses changed at SPS. Maintenance performed during sps

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-12:
    “Stand elevator inserts indentification” – The inserts for the stand elevator could be difficult to identify and the wrong size insert could easily be installed. It is recommended to improve the colour coding of the stand elevator insert plates.

    Improve the colour coding of the stand elevator insert plates.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Stand Insert plates have been re-painted. This will also be done regularly when needed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-13:
    “Elevator insert change out” – BX elevator inserts are colour coded but paint on some items is partially worn off. It is recommended to repaint the set to avoid confusion

    Repaint elevator inserts.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Elevator inserts have been re-painted. This will also be done regularly when needed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-14:
    “Drill String Inspection” – Clarify drill string inspection string before start of Tomcat well i.e. will all drill string and BHA components be backloaded at end of Shell PP&A campaign and a newly-inspected string be mobilized prior to Tomcat.

    Please specify if newly inspected drill string will be mobilised prior to Tomcat.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Drill string is changed out once a year. Not need to change out before march. BHA collars/HWDP and landing stiring is changed out on rotational hrs. 250 hrs.
    18.12.24 Open until Kjøttkake.
    15.01.2025 Will use existing pipe

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-15:
    “FOSV Key” – From previous inspection but still valid: the operating key for the FOSV was a conventional Allen key fitted with a lanyard. This could be lost or dropped down the hole during make up, possible preventing well securement during an emergency. It is recommended that the Key for the FOSV have a large ring welded to it (eg old ring gasket) to prevent it from being dropped down the hole during installation/operation.

    Please consider welding a large ring to the FOS

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Ongoing. New finish date 01.02.25. But the allan key is rental equipment and its fitted with securing wire.
    18.12.24 Will check with DSL
    20.01.25 REN (DSL): Ring er sveist på nøkkel til kelly cocker.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-16:
    “Cement unit handover” – Halliburton and Baker to provide details of cement unit handover plan to ensure smooth and efficient handover. Focus on checking certification of all Pressure Relief Valves (PRVs) on unit.

    PUN to ensure that Halliburton gets a proper handover from Baker with focus on checking certification on all pressure relief valves.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Safety Officer
    Annen tiltaksansvarlig person: Halliburton Cementer

    13.11.24 KWIR I received the handover papers from Halliburton Cementer. File attached to this activity

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-17:
    “Halliburton foam cement check-up visit” – DSY has performed a number of foam cement jobs with Halliburton. A site visit should still be made by Halliburton to verify that all service tie-ins on the sack store roof are suitable for an efficient rig-up on the Tomcat and Kjøttkake wells.

    PUN to ensure Halliburton foam cement set-up plans are in place.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    Two cement jobs performed on Tomcat. System up and running.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-18:
    “Skip Station and skip loading distributer” – The skip station will need to be reinstalled prior to the Tomcat operations. This includes reinstalling the skip loading distributer.

    PUN and Odfjell to ensure re-installation of skip station and skip loading.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

    Skip station is up and running

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-19:
    “ISO tank area” – RIM deck to be removed, install 6 x weight deck and 6 ISO tanks prior to the Tomcat operations.

    PUN and Odfjell to ensure re-installation of ISO tank area.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    5/11: on Rig visit – observed to be in place. Awaiting confirmation on installation status
    System is Up and running

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-20:
    “Slop treatment Platform – Soiltech” – OTS unit to be removed and Soiltech unit to be installed prior to the Tomcat operations

    PUN to ensure that Soiltech unit is re-installed

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    18.12.3034 Unit is up and running. However missing smoke will be installed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-21:
    “Enhanced Drilling RMR check-up visit” – DSY has performed a number of RMR jobs using Enhanced Drilling. A site visit should still be made by ED to verify that all service tie-ins on the port aft main deck RMR area are suitable for an efficient rig-up on Tomcat.

    PUN and Odfjell to ensure RMR system is rigged up prior to Tomcat operation.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Vambheim Endre

    RMR system rigged up and installed. Closed in Synergi.

  • Improvement

    Closed


    Closed


    Deadline was:

    IS-2 Floor In shower in cabin 226 was soiled

    Clean or change out flooring

    This have been corrected



Additional Documentation


WE-EA-2024-6-Joint-Rig-Intake-Report_-Rev.-01-signed.pdf, PGNIG-TOMC-D-RA-012-Joint-Rig-Inspection-DSY_rev.-01-signed.pdf, 239809-•-PUN-DNO-Joint-Rig-Inspection-Deepsea-Yantai-•-Synergi-Life.pdf, 239809-•-PUN-DNO-Joint-Rig-Inspection-Deepsea-Yantai-•-Synergi-Life-1.pdf




New Audit Report

You do not have permission to view this form.


\n


Odfjell

No person selected

Report No.

6879
Joint Rig Inspection – DSY

Type of audit

Rig Intake
Odfjell

Auditee/Customer

Odfjell
Orlen Upstream Norway & DNO Norge

Date

2024/11/06

396 days ago

Findings

23
Number of findings

Status

Closed
Rig Intake


Joint Rig Inspection – DSY
Summary

As part of rig intake and preparations for PUN’s and DNO’s exploration wells, Tomcat and Kjøttkake, a rig inspection was carried out when the rig was at on contract with Shell on Knarr.
The Rig Intake Team (RIT) would like to acknowledge the support provided by Odfjell and service personnel during the verification. All persons involved from Odfjell and Service Companies were open, extremely
helpful and positive.

The overall impression is that the rig is effectively managed by Odfjell, rig equipment is in uniformly good condition and housekeeping is maintained at a very high standard.

The inspection team identified 23 findings, zero (0) non-conformances, two (2) observation and twentyone (21) improvement points. The findings are listed in chapter 4.

Odfjell is requested to respond within two weeks (ten working days) of receiving this report on how they intended to handle the findings and sending WE the required information.

Findings

  • Observation

    Closed


    Closed


    Deadline was:

    Rig Inspection – O-1
    “Broken guard on pillar drill” – The guard on the rotating drill chuck on the pillar drill in the welder’s shop was broken.

    Replace ASAP.

    11.11.24 KNB: Dette er utbedret nå.

  • Observation

    Closed


    Closed


    Deadline was:

    Rig Inspection – O-2
    “Liner covers” – Covers observed to be raised up. Covers to be retained closed during operation.

    Covers to be retained closed during operation

    OD frist: 01.02.2025

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-1:
    “Labeling of handheld tools” – The tools were not labelled according to SfS recommendation 044N Labelling and use of handheld tools. The guideline was published in 2021.

    More resources should be available to get this in place.

    12.11.24 KWIR We have an ongoing project of marking HAVS Tools

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Safety Officer

    21.11.24: EKE. We have received new lists from ISOS. The lists are posted on the tool cabinet for the deck crew, mechanics, welders cabinet. We have also labelled the tools with stickers showing category of tool.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-3:
    “Simulator training for medics” – When the duty doctor arrangement is sentralised it is required to have telemedecine connected to the duty doctor an the Medics shall be trainied in the emergeny medical treatment protocols (Simulator Training)

    Schedule Simulator training for medics

    Dette er et krav og må være på plass før DNO / kjøttkake Offshore norge sitt krav 014

    Tiltaksansvarlig bruker: Snekkevik Odd-Egil (DSY Rig Manager)

    Info from Odfjell: Supplier of course is Prometheus (previous Safeguard)
    Two days course: Live tissue / Simulator training.
    Scheduled Week 44 and 48 – 2024

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-4:
    “NDT inspection of loose drilling equipment” – All this equipment was last inspected August 2023. Now due for reinspection.

    Odfjell to schedule reinspection ASAP.

    12.11.24 Bjbe Axxes performed inspection april 2024

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-5:
    “Rig blackout test” – Odfjell to report back when reasons for deadship generator failing to start during blackout test have been established

    Send investigation report or result from new test to RIL

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Andersen Kenneth Holm

    Repaired

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-6:
    “Upcoming SPS” – The SPS workscope is run by a dedicated shoreside based team commissioning and reviewing equipment condition assessments then mobilising mechanics, electricians, vendor representatives eg NOV, NDT specialists etc to visit the rig. A substantial amount of SPS work appears to have been completed ahead of the yard stay.

    Please provide an overview of Scope of Work required for the SPS Quayside period towards the end of the Shell PPP&A campaign.
    Please also provide a Scope of Work for any campaign of “rig maintenance catch-up” to be performed during the SPS Quayside period.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Andersen Kenneth Holm

    SPS is complete. OD has high focus on bringing the maintenance numbers down. This is followed up during the

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-7:
    “Wire lubrication” – Some of the crane wire looked dry.

    Recommend that lubrication routines are reviewed to ascertain if more lubrication required.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-8:
    “Air conditioning, operator’s cabin, starboard crane” – A/C unit was out of order in starboard crane.

    Please report when replaced and temporary fan removed from crane operator’s cabin

    Tiltaksansvarlig bruker: DSY Technical Section Leader

    12.11.2024 RBR: A/C unit replaced

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-9:
    “Machinery room work bench, starboard crane” – House keeping could be improved and the bench tidied up.

    Improve housekeeping in machine room, starboard crane

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-10:
    “Fire fighting provision in crane” – Improvement Suggestion from previous inspection which is still valid: the crane machinery room has a large inventory of hydraulic oil. In the event of a leak in the hydraulic system this oil can be released under pressure and vaporised. Depending on the oil type, this could represent a fire hazard if ignited. A single portable fire extinguisher may not be adequate for a fire in the crane machinery room. It is suggested that this is evaluated further.

    Evaluate further requirements for firefighting equipment in crane machinery room.

    15.01.2025 Evaluation is that there is no need for additional fire extinguisher

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-11:
    “Hydraracker maintenance” – From last inspection but still valid: The Hydraracker does not have redundancy, failure of it during service would result in downtime. Given the criticality and lack of redundancy of the Hydraracker.

    Please perform a detailed review of Hydraracker maintenance condition.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Technical Section Leader

    18.12.24 Hoses changed at SPS. Maintenance performed during sps

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-12:
    “Stand elevator inserts indentification” – The inserts for the stand elevator could be difficult to identify and the wrong size insert could easily be installed. It is recommended to improve the colour coding of the stand elevator insert plates.

    Improve the colour coding of the stand elevator insert plates.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Stand Insert plates have been re-painted. This will also be done regularly when needed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-13:
    “Elevator insert change out” – BX elevator inserts are colour coded but paint on some items is partially worn off. It is recommended to repaint the set to avoid confusion

    Repaint elevator inserts.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Elevator inserts have been re-painted. This will also be done regularly when needed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-14:
    “Drill String Inspection” – Clarify drill string inspection string before start of Tomcat well i.e. will all drill string and BHA components be backloaded at end of Shell PP&A campaign and a newly-inspected string be mobilized prior to Tomcat.

    Please specify if newly inspected drill string will be mobilised prior to Tomcat.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Drill string is changed out once a year. Not need to change out before march. BHA collars/HWDP and landing stiring is changed out on rotational hrs. 250 hrs.
    18.12.24 Open until Kjøttkake.
    15.01.2025 Will use existing pipe

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-15:
    “FOSV Key” – From previous inspection but still valid: the operating key for the FOSV was a conventional Allen key fitted with a lanyard. This could be lost or dropped down the hole during make up, possible preventing well securement during an emergency. It is recommended that the Key for the FOSV have a large ring welded to it (eg old ring gasket) to prevent it from being dropped down the hole during installation/operation.

    Please consider welding a large ring to the FOS

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Drilling Section Leader

    Ongoing. New finish date 01.02.25. But the allan key is rental equipment and its fitted with securing wire.
    18.12.24 Will check with DSL
    20.01.25 REN (DSL): Ring er sveist på nøkkel til kelly cocker.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-16:
    “Cement unit handover” – Halliburton and Baker to provide details of cement unit handover plan to ensure smooth and efficient handover. Focus on checking certification of all Pressure Relief Valves (PRVs) on unit.

    PUN to ensure that Halliburton gets a proper handover from Baker with focus on checking certification on all pressure relief valves.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Safety Officer
    Annen tiltaksansvarlig person: Halliburton Cementer

    13.11.24 KWIR I received the handover papers from Halliburton Cementer. File attached to this activity

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-17:
    “Halliburton foam cement check-up visit” – DSY has performed a number of foam cement jobs with Halliburton. A site visit should still be made by Halliburton to verify that all service tie-ins on the sack store roof are suitable for an efficient rig-up on the Tomcat and Kjøttkake wells.

    PUN to ensure Halliburton foam cement set-up plans are in place.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    Two cement jobs performed on Tomcat. System up and running.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-18:
    “Skip Station and skip loading distributer” – The skip station will need to be reinstalled prior to the Tomcat operations. This includes reinstalling the skip loading distributer.

    PUN and Odfjell to ensure re-installation of skip station and skip loading.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Stability Section Leader

    Skip station is up and running

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-19:
    “ISO tank area” – RIM deck to be removed, install 6 x weight deck and 6 ISO tanks prior to the Tomcat operations.

    PUN and Odfjell to ensure re-installation of ISO tank area.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    5/11: on Rig visit – observed to be in place. Awaiting confirmation on installation status
    System is Up and running

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-20:
    “Slop treatment Platform – Soiltech” – OTS unit to be removed and Soiltech unit to be installed prior to the Tomcat operations

    PUN to ensure that Soiltech unit is re-installed

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: DSY Offshore Installation Manager

    18.12.3034 Unit is up and running. However missing smoke will be installed.

  • Improvement

    Closed


    Closed


    Deadline was:

    Rig Inspection – IS-21:
    “Enhanced Drilling RMR check-up visit” – DSY has performed a number of RMR jobs using Enhanced Drilling. A site visit should still be made by ED to verify that all service tie-ins on the port aft main deck RMR area are suitable for an efficient rig-up on Tomcat.

    PUN and Odfjell to ensure RMR system is rigged up prior to Tomcat operation.

    OD frist: 01.02.2025
    Tiltaksansvarlig bruker: Vambheim Endre

    RMR system rigged up and installed. Closed in Synergi.

  • Improvement

    Closed


    Closed


    Deadline was:

    IS-2 Floor In shower in cabin 226 was soiled

    Clean or change out flooring

    This have been corrected



Additional Documentation


WE-EA-2024-6-Joint-Rig-Intake-Report_-Rev.-01-signed.pdf, PGNIG-TOMC-D-RA-012-Joint-Rig-Inspection-DSY_rev.-01-signed.pdf, 239809-•-PUN-DNO-Joint-Rig-Inspection-Deepsea-Yantai-•-Synergi-Life.pdf, 239809-•-PUN-DNO-Joint-Rig-Inspection-Deepsea-Yantai-•-Synergi-Life-1.pdf



\n”}}]}]}]},{“type”:”section”,”props”:{“class”:”uk-hidden”,”id”:”newreport”,”image_position”:”center-center”,”padding”:”none”,”style”:”default”,”title_breakpoint”:”xl”,”title_position”:”top-left”,”title_rotation”:”left”,”vertical_align”:””,”width”:”default”},”children”:[{“type”:”row”,”children”:[{“type”:”column”,”props”:{“image_position”:”center-center”,”position_sticky_breakpoint”:”m”},”children”:[{“type”:”html”,”props”:{“content”:”

\n

\n

New Audit Report