Management Review for 2024
Summary
Findings
-
An IMP after DNO’s audit in November 2024 was to secure better follow-up of actions from the Management Review
To follow-up the actions in WEReport
All agreed actions registered in WEReport
-
Agree with Lars Solvang on CV formats and how to easily store
-
As Magnet JQS is a platform that operators use to check suppliers, our site must reflect our business and services better
Stig, Morten and Sigve to assist
-
Publish statement on the Transparency Act by 01.06.25
Use the one from 2024 as basis
-
To be according to Magnet JQS requirements, actions need to be implemented to secure that WE work according to
– Make a GAP towards the standard – Lars with support from the Management Team
– Update «How WE Manage Information and Computer Technology” procedure – Lars/Anniken
– Updated our Regulatory overview – Anniken -
Secure update of the Enterprise risk register and use time to get familiar with the ESG risk register
Conduct a risk meeting and secure regular info in management meetings
-
Utilise HUMA better
Implement job descriptions, competence matrix, new employment contracts and personnel handbook
-
There is still a need for “investing” in having different standards available through Standard.no
Agree on when and what
18.03.25: Contacted Standard Online to get an overview of standards we have available through our subscription
-
We must get better to require feedback from our clients on satisfaction on our deliveries in each project
– Have a run-through of the template – Roel, Stig, Morten – Sigve QA
– Secure storage of the ones we have received since 2017 – Morten
– Secure feedback on ongoing and coming projects and that they are signed by us and client – DSIs -
Update “How WE Contract and Manage Suppliers” with how WE handle Human rights and due dill towards suppliers
Draft (rev. 05) started on 24.02.2025
-
For our suite of contracts: Issue RfQs and sign new FAs
– Issue RfQ for Completion, OCTG, Drilling and PP&A Services Q2 valid for 26-28
– Sign new FA with Baker, Odfjell, Hunting, Schlumberger -
Introduce project KO meetings and EoW check list in all projects
DSIs are responsible for implementing this in their projects
06.03.2025: Morten made a suggestion on how to kick off projects with a proposed check list, presentation and risk assessment. Team should be aligned on day 1 of the project to avoid any confusion with regards to deliverables or details. This should save time and make sure that we actually are one team moving toward solving the task together and also ensure that we are not moving out of scope without getting compensated.
New Audit Report
\n
WE

|
Report No.
|
8442 |
|
Type of audit
|
Internal Audits |
|
Auditee/Customer
|
WE |
|
Date
|
2025/03/13 |
|
Findings
|
12 |
|
Status
|
In process |
Management Review for 2024
Summary
Findings
-
An IMP after DNO’s audit in November 2024 was to secure better follow-up of actions from the Management Review
To follow-up the actions in WEReport
All agreed actions registered in WEReport
-
Agree with Lars Solvang on CV formats and how to easily store
-
As Magnet JQS is a platform that operators use to check suppliers, our site must reflect our business and services better
Stig, Morten and Sigve to assist
-
Publish statement on the Transparency Act by 01.06.25
Use the one from 2024 as basis
-
To be according to Magnet JQS requirements, actions need to be implemented to secure that WE work according to
– Make a GAP towards the standard – Lars with support from the Management Team
– Update «How WE Manage Information and Computer Technology” procedure – Lars/Anniken
– Updated our Regulatory overview – Anniken -
Secure update of the Enterprise risk register and use time to get familiar with the ESG risk register
Conduct a risk meeting and secure regular info in management meetings
-
Utilise HUMA better
Implement job descriptions, competence matrix, new employment contracts and personnel handbook
-
There is still a need for “investing” in having different standards available through Standard.no
Agree on when and what
18.03.25: Contacted Standard Online to get an overview of standards we have available through our subscription
-
We must get better to require feedback from our clients on satisfaction on our deliveries in each project
– Have a run-through of the template – Roel, Stig, Morten – Sigve QA
– Secure storage of the ones we have received since 2017 – Morten
– Secure feedback on ongoing and coming projects and that they are signed by us and client – DSIs -
Update “How WE Contract and Manage Suppliers” with how WE handle Human rights and due dill towards suppliers
Draft (rev. 05) started on 24.02.2025
-
For our suite of contracts: Issue RfQs and sign new FAs
– Issue RfQ for Completion, OCTG, Drilling and PP&A Services Q2 valid for 26-28
– Sign new FA with Baker, Odfjell, Hunting, Schlumberger -
Introduce project KO meetings and EoW check list in all projects
DSIs are responsible for implementing this in their projects
06.03.2025: Morten made a suggestion on how to kick off projects with a proposed check list, presentation and risk assessment. Team should be aligned on day 1 of the project to avoid any confusion with regards to deliverables or details. This should save time and make sure that we actually are one team moving toward solving the task together and also ensure that we are not moving out of scope without getting compensated.