Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Wellesley
6254 – Wellesley

COSLPromoter, COSL Promoter Drilling Operational 35/11-5, 39/11-29S
Toppand East
Reservoir section 30/05/2024 Needed to change the BX inserts. Resulting in 30 min rig time and unnecessary manual handling.

Drilling Engineer / Morten Laget



PDF


Edit


Wellesley
467 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 31/08/2020 More manual handling and time spent in addition to less efficient handling when not having all BHA . . .

Drilling Engineer


PDF


Edit