Lesson Learned





By: Karina Helle

Report No.

1220

Discipline/Origin

Drilling
Experience Transfer Meeting

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2012/04/15
4983 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
Negative

Borgland Dolphin


What happened in Production section:
DONG handover documentation: Started to get backflow when running the last 10 joints of blank pipe due to large OD of Swellpackers and heavy mud system. Had to run in slowly with the remaining joints to control the backflow. After picking up the LH and SwivelMaster we had to screw in the topdrive on each connection to prevent mudspill. Had to change saversub as we were running a mix of 5″ and 5½” HWDP. Decided to pump a slug of 1,85 SG OBM (5 m3)

External Actions

Change the OCG to prevent using excessive time on this in the future. Prepare a pit with heavy LSOBM(10-15 m3?) Make up topdrive on the first 5 stands after the Swivelmaster and pump a 5 m3 slug.