By: Drilling Supervisor

Report No.

1416

Discipline/Origin

Drilling
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/04/10
1702 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Borgland Dolphin


What happened in P&A:
Had only 1 Dolphin sub sea engineer. He had to work overtime, and OIM had to make deviation. The sub sea worked more than 16 hrs in one stretch. His presence was on the critical path of the operation.

What Was Planned

Land the lower marine riser package, disconnect the BOP from x-mas tree, function test BOP, etc. Lots of BOP work.

What Was Learned

It was not sufficient with only 1 sub sea engineer onboard during this phase of the operation

What Actions Are Required

Consider having 2 subsea engineers (24 hr coverage) in P&A operations where BOP is jumped between well and lifted off HXT and wellhead frequently.