WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

1529

Discipline/Origin

Drilling
Own Experience

Well

Fat Canyon
PL937

Date created

2021/10/01
1527 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Casing
Negative

Borgland Dolphin


What happened in Top hole:
The conductor tally was not ready until last minute, and this created stress for the offshore personnel to space out the 36″ x 42″ BHA properly.

What Was Planned

Planned to take Conductor onboard the rig before the rig move to Fat Canyon location. This, however, was not done, and the conductor remained on the boat until the rig was on location and hooked up to anchors.

What Was Learned

Have conductor on rig during sail to be able to measure and produce tally, or have Dril-Quip produce tally onshore before shipment.