What happened in :
Several days with HK delay because of seastate 6 resitrictions and HTI warning. Afternoon Flight ended up with night criteria.

What Was Planned

Helicopter Flight in the afternoon, On time departure.

What Was Learned

Night criteria reduce the chance for flight alot, with regard to weather periode with seastate 6 and HTI.

What Actions Are Required

Include flight schedule in RFQ and evaluation. Aim for day-light flight.