WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

201

Discipline/Origin

Drilling
No origin

Well

Kallåsen
35/12-6 S

Date created

2019/02/05
2496 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Rig specific
Negative

Transocean Arctic


What happened in Production section:
Tried to shear OBM mud in pits before drilling the 12 1/4″ section. At this time the well and all surface lines contained SW. Plan was to RIH with BHA in SW, fill pipe with SW, function test MWD with SW etc.

What Was Planned

Shear OBM in pits prior to drilling the 12 1/4″ section.

What Was Learned

If rig would pump OBM from mud pump into mud standpipe to shear mud in pit, one would pollute SW with OBM, and get this into well when testing MWS and filling pipe to trip in. It was not possible to split the standpipe in two, one for OBM and one for SW. Consequence is one has to shear OBM through bit and control ROP until low end rheology & 3 rpm reading are up within spec.

What Actions Are Required

Do not plan to shear mud in pits in similar operations. ?