What happened in Top hole:
We could not store enough Tuned Light cement on two cmt silos on the rig to get the required volume of cement slurry.

What Was Planned

Cement 500 m long 20″ casing with OH 100% excess. 139 m3 cmt slurry.

What Was Learned

Tuned light cement is much lighter than normal cmt, only able to get 50 MT Tuned Light on each cmt silo.

What Actions Are Required

We must plan to use all 3 available cement silos when planning to cement surface casing over 400 m length on Borgland Dolphin. That means all 3 Silos must be empty before spud of a exploration well.

What Was Done

We had to empty Silo 8 of Expanda DM cement to a supply boat, and re-load it with 50 MT Tuned Light cement. This was discovered only 2days before the cement job, so we were lucky to spot the problem, and to resolve the problem.