What happened in P&A:
Clamps holding the control lines (polyoil clamps) had disintegrated. Tubing had to be cut after it got stuck when pulling it with the control lines coiling itself on the between tubing and casing.

What Was Planned

Pulling completion (tubing and control lines) after cutting the tubing just above the production packer.

What Was Learned

Fishing of control lines is difficult.

What Actions Are Required

If these types of clamps have been used a tailored fishing package should be made available.