WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

237

Discipline/Origin

Well test
No origin

Well

Grosbeak West
35/11-21 S

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Transocean Arctic


What happened in Reservoir section:
Had to break and re-M/U several joints on Vallourec 7″ 32# P-110 Vam 21 liner due to coating on 7″ liner sticking on dices.

What Was Planned

Well test, M/U 7″ liner