WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

247

Discipline/Origin

Drilling
No origin

Well

Grosbeak
35/11-21 A

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Transocean Arctic


What happened in Reservoir section:
During sampling it was found out that the exit point was not consistent to be on top of the FTWT tool string. After discussions with Schlumberger, is was found out that there was an exit port 52 m lower than the upper exit port was used during sampling (pending on formation fluids/stations). This explained why the gas level did not go down when circulating out formation fluids.

What Was Planned

Run FTWT.

What Was Learned

Lacked knowledge and experience with the FTWT tool. The information and the complexity of the tool should have been informed at an earlier stage from Slb. One person had to cover 24 hr operation.

What Actions Are Required

Mobilize two experienced personnel for similar operations, to have one on each shift.