Report No.

280

Discipline/Origin

Drilling
No origin

Well

Rungne
30/6-30

Date created

2019/10/01
2258 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
N/A

Transocean Arctic


What happened in P&A:
Weatherford Whirl Tool, part of Wellbore Cleanout Tools used for brushing riser and jetting BOP. OD on tool is 13 3/8″.

What Was Planned

Whirl Tool Weatherford

What Was Learned

Need to remember to space-out to stay above the 20″ x 13 3/8″ XO. Easily overlooked.

What Actions Are Required

NA