WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

316

Discipline/Origin

No origin

Well

Canela
6507/7-16 S

Date created

2019/01/07
2525 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
Positive

Island Innovator


What happened in Production section:
Drilled section with planned mud and mud weight without problems with cavings. Cavaings identified at TD and MW increased to 1.52 sg in two stages.

What Was Planned

Drill long 12 1/4″ section through Hordaland, Rogaland, Shetlandusing 1.48 sg OBM.

What Was Learned

OBM worked well for stabilizing the formations drilled, allowing for a 3-string design.

What Actions Are Required

Use of OBM for this section on future wells in the area.

EDITOR


CLOSE LL (testing)





New Lesson Learned

You do not have permission to view this form.