What happened in Planning:
In order to ensure compliance with NORSOK, a verification of the conductor analysis was done by DNV GL.

What Was Planned

Using Fugro for performing conductor analysis.

What Was Learned

This process dragged out in time. Must start very early in well planning due to commitment of Long lead items. Several load cases were adjusted in the final version compared to the conservative draft (pre DNV GL verification).

What Actions Are Required

Evaluate to use Fugro (with 3rd party verification) or another provider for conductor analysis.