362

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2019/10/22
2238 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

BHA
Negative

Deepsea Nordkapp


What happened in Reservoir section:
Drilled to core point and POOH. Experienced tool problems on ADR and XBAT (Sonic). HAL onshore was not able to say what caused the problem hence it was decided to change the full BHA.
Ran in with backup tools.

What Was Planned

MWD

What Was Learned

In this case there would not be enough time to mobilize new B/U tools, which put the operation at risk for downtime.

What Actions Are Required

Important that the equipment is checked ASAP on the rig to give the team time to mobilise new equipment.