WE Report

Lessons Learned

Lesson Learned





By: Karina Helle

Report No.

1155

Discipline/Origin

Drilling
Experience Transfer Meeting

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2020/09/08
1916 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Experience Transfer Meeting
Negative

Borgland Dolphin


Section N/A. What happened:
Initial engineering not completed before select phase started.
Several several MoCs.

What Was Planned

Select phase not completed before define phase started.

What Was Learned

Poor communication and project management.

What Was Done

Oselvar: Covered in PIMM

External Actions

Actions for Oselvar: “Secure alignement in the project.
Use the project meetings to aligne
Set dates for finalization

Secure good communication in the project
Examine MoC approvals to secure a smooth process and less time waiting for sollution”

What Was Done

Oselvar: Covered in PIMM