WE Report

Lessons Learned

Lesson Learned





By: Rob Banbury

Report No.

483

Discipline/Origin

Drilling
No origin

Well

Schweinsteiger
6204/11-3

Date created

2020/09/05
1919 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Borgland Dolphin


What happened in Surface section:
Ran MPT tool dressed to pull extended wear bushing. Successfully engaged and sheared out but hung up in lower annular annular. Retrieved by pumping up choke line to wash wear bushing while pulling.

What Was Planned

Pull extended wear bushing prior to running 9 5/8″ casing

What Was Learned

Wear bushing and DrilQuip MPT were both packed off with cuttings when retrieved to surface. RIH jet sub and jetted wellhead and surface casing down to 3m past 13 3/8″ x 20″ crossover.

What Actions Are Required

Consider in future running jet sub minimum 1 stand below MPT. Jet not only BOP but wellhead, wear bushing itself before unlatching and surface casing all the way down to 13 3/8″ x 20″ crossover before attempting to unlatch and pull through BOP into riser.