WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

4913

Discipline/Origin

Drilling
No origin

Well

Copernicus
6608/1-1 S

Date created

2022/09/23
1170 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Positive

Deepsea Yantai


What happened in P&A:
When pulling the conductor there was no cement stuck to it due to use of protane wrapping on the condcutor.

What Was Planned

The conductor was run with a protane wrapping

What Was Learned

Good measures to use protane wrapping on the conductor. Less cement to be washed off in the moonpool POOH with the cut WH.

What Actions Are Required

Continue to run the conductor with protane wrapping.

EDITOR


CLOSE LL (testing)





New Lesson Learned