WE Report

Lessons Learned

Lesson Learned





By: Sander Schaathun

Report No.

5114

Discipline/Origin

Drilling
No origin

Well

Eirik (OMV)No well selected

Date created

2023/03/30
982 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
No classification

Deepsea Yantai


What happened in Intermediate section:
Experienced higher pore pressure earlier than expected. Had enough to weight up active from 1,44 to 1,57, but not enough Barite to weight up mud to, in this case 1,6 Sg.

What Was Planned

Higher focus on Barite onboard as drilling closer to 12. 1/4″ TD. MW at 1,44 was planned.

What Was Learned

Have barite on all boats coming to location? Always one boat on location with barite? Difficulties delivering barite. Evaluate to have heavier back up mud have a min of 100 T barite on each boat.

What Actions Are Required

Define in planning phase for how much extra MW can potentially be needed if high PP estimate comes in.

Additional Documentation


LL-from-Eirik-OMV-2.pdf

EDITOR


CLOSE LL (testing)





New Lesson Learned