By: Drilling Engineer

Report No.

5128

Discipline/Origin

Logistics
No origin

Well

Carmen
35/10-10S

Date created

2023/04/10
971 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Yantai


What happened in Surface section:
Logistical problems when Shoe track joints are placed on top of all other CSG on the boat. Shoetrack joints to be segregated on the boat. It is usually the last load onboard the rig from the boat.

What Was Learned

Segregate Slicks/Centraliser/Shoetrack when loading the boat.

What Actions Are Required

Segregate Slicks/Centraliser/Shoetrack when loading the boat.