Lesson Learned





By: Drilling Engineer

Report No.

5138

Discipline/Origin

Drilling
No origin

Well

Carmen
35/10-10S

Date created

2023/04/13
968 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Yantai


What happened in Surface section:
Total NPT: 11.25 hrs
Cost: 2 343 750 NOK

LARS lost communication with SubSea pump. Troubleshot same.
Consulted with shore-based support on way ahead.
– Discussed recommendation to bypass slip rings on fibreoptic interface to establish whether fault on surface or below sea level.
Bypassed slip rings on fibre-optic interface in LARS and reconnected fibre optic connections.
– Confirmed electrical communication with SubSea pump with slip rings bypassed, indicating fault on surface.
Continued RIS SubSea pump from 75 m to 180 m with slip rings bypassed and confirmed communication with pump.
LARS lost communication again with SubSea pump at 180 m. Troubleshot same.
Unable to diagnose fault. Commenced retrieval of RMR.
SubSea pump to surface for further investigation. Pump on surface at 0700 hrs.
Performed repair of RMR subsea pump.
– Diagnosed a faulty fibre optical jumper between oil-filled connection box and pressure bottle. Replaced jumper and confirmed communication to pump through umbilical.
– Commenced RIS with subsea pump at 0830 hrs. Pump at 180 m 10:00 hrs.

What Was Planned

Prepare for RMR ops – Run SMO and suction hose to bed