Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5139

Discipline/Origin

Drilling
No origin

Well

Carmen
35/10-10S

Date created

2023/04/13
968 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Casing
Negative

Deepsea Yantai


What happened in Surface section:
NPT: 1.25 hrs
Cost: 260 417 NOK

Performed mechanical repair on make/break cylinder on casing tong.

What Was Planned

Run 20″ Casing

EDITOR