WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5159

Discipline/Origin

Drilling
No origin

Well

Carmen
35/10-10S

Date created

2023/04/24
957 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
Negative

Deepsea Yantai


What happened in Production section:
Downtime due to reduced ROP after going to max ROP of 75 m/hr:
– Started with 30 m/hr
– Jumped up to 60 m/hr
– Jumped further to 75 m/hr
– ROP was reduced to 20-40 m/hr for a period due to the plugging

What Was Planned

Using Lube mud to make sure that pump should work efficiently at the start og the section and to avoid plugging.

What Was Learned

More time should be used ramping up ROP to run the system warm and not cause any plugging.
Too low time increments between jumps caused plugging in cutting system (ISO-tanks)

What Actions Are Required

Use longer time increments between jumps of ROP.