Report No.

246

Discipline/Origin

Drilling
No origin

Well

Grosbeak
35/11-21 A

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Transocean Arctic


What happened in Reservoir section:
Inner bushing with cut-out for wireline was not mobilized for this wireline conveyed logging job. A set of bushings was ordered the day before logging commenced, but could not be lifted onto rig due to weather. The rig modified their own inner bushings, and grinded a groove into the bushings.

What Was Planned

Pipe conveyed logging with slotted inner bushing.

What Was Learned

Certified slotted bushings proved inferior to rig modified items. This because the slot was wider than required and spanned the ends of the two halves, which allowed the cable to be slightly flattened. Would be better to design a slot “just wide enough” for the cable in use.

What Actions Are Required

Schlumberger should flag the requirement at the job planning stage.