Report No.

407

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2095 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
Dril-Quip – new cost items appear on invoices, not covered in contract. 

What Was Learned

CC to verify MSR with Lead Engineer against frame agreement
Delays and complicates invoice approval process. Could cause issues with regards to procurement guidelines and audits. All cost items in Cost estimate to be referenced according to contract ref. 

What Actions Are Required

CC to verify MSR with Lead Engineer against frame agreement
Delays and complicates invoice approval process. Could cause issues with regards to procurement guidelines and audits. All cost items in Cost estimate to be referenced according to contract ref. 