Lesson Learned





By: Steinar Aarnes

Report No.

2319

Discipline/Origin

Drilling
Own Experience

Well

Fat Canyon
6306/3-1 S

Date created

2021/12/09
1458 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Borgland Dolphin


What happened in Top hole:
Encountered several shallow gas zones. The decision to use and mobilize foam cement took some time.

This forced the client to take on extremely expensive spot-market vessels to deliver equipment and rig up.

What Was Planned

Drill top hole section without encountering shallow gas

What Was Learned

In places where shallow gas is somewhat expected, foam cement equipment should be mobilized and kept ready incase its needed. It is cheaper to start mobilizing equipment and demobilizing it, rather then having operational downtime and also taking on spot-market vessels.

What Actions Are Required

No actions required as this is usally up to the clients. However, it can be recommended to different clients based on this experience.