WE Report

Lessons Learned

Lesson Learned



INTERNAL



No user selected

Report No.

404

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2095 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
Pro-forma invoice check & approval process – supposed to use max. 5 working days, overrun for approx 90% of all invoices (used several weeks per invoice)

What Was Learned

Internal QC and review of AfE, Quotes, MSR, etc before invoices start dropping into mailbox
Ensure that service company coordinator and cost controller understands quotes / delivery
RfQ owner should be available for questions/clarifications
All agreements in connection with RfQ should be documented and stored on PP
Not possible to verify invoiced offshore personnel days against POB in Timetracker. Offshore (LE/DSV?) to update according to actual (update previous day once inputting forecast for same day)
Lack of resources? Back-up for vacations?

What Actions Are Required

Internal QC and review of AfE, Quotes, MSR, etc before invoices start dropping into mailbox
Ensure that service company coordinator and cost controller understands quotes / delivery
RfQ owner should be available for questions/clarifications
All agreements in connection with RfQ should be documented and stored on PP
Not possible to verify invoiced offshore personnel days against POB in Timetracker. Offshore (LE/DSV?) to update according to actual (update previous day once inputting forecast for same day)
Lack of resources? Back-up for vacations?