What happened in Top hole:
Movement of conductor. Adjusted scaffold at diverter platform. Installed chain hoist horizontally in moonpool to stop movement.

What Was Planned

Do the rough cut at 4.402 m below RKB. Conductor tensioned up with tension ring to 150 MT. Not planned to install any horizontal tensioning at this stage.

What Was Learned

Evaluate to install horizontal tension system before making the rough cut to avoid any movement of conductor after cut made.

What Actions Are Required

Evaluate to implement for next operation.