What happened in Top hole:
The hammer and drive sleeve were made up on the rig by Expro crew. The hammer and drive sleeve were shipped back as one item.

What Was Planned

The hammer was planned out separate from the drive sleeve.

What Was Learned

Beneficial if it’s sent out in one component/pre-made up on shoe. Less heavy lifts on the rig and time saving.

What Actions Are Required

Evaluate possibilities for sending out the drive sleeve and hammer pre-made for future hammering operations.