By: Lene Lomeland

Report No.

6970

Discipline/Origin

Drilling
No origin

Well

Falstaff
2/6-7 S

Date created

2024/11/11
390 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

What happened in Reservoir section:
When RIH with Whipstock/Milling BHA to set the Whipstock, it took weight in the 9 5/8” liner – not able to get through with 10 MT WOB.
The drift BHA had an OD of 8.5”. The Lead Mill on the Whipstock/Milling BHA had an OD of 8.515”, same as the smallest ID in the Liner Hanger. Had to polish the 9 5/8” liner hanger area to be able to get through with Whipstock/Milling BHA.

What Was Planned

RIH with Drift BHA when tagging P&A cement plug #1. The drift run to verify that we could run the Whipstock/Milling BHA in well without restrictions.

What Was Learned

To run drift run with the same size as the BHA planned to go in hole.