By: Christina Sæland Rødne

Report No.

4764

Discipline/Origin

HSEQ
Own Experience

Well

6608/1-1No well selected

Date created

2022/08/23
1201 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
N/A

Deepsea Yantai


What happened in Other:
DSY waste management plan is according to IMO, and does not conflict with NOROG 093. It was therefore decided not to create one for the project, as the rig is satisfied with their own plan and that WE/PGNiG will only have the rig for 30-40 days.

What Was Planned

Create a waste management plan if the rig’s plan is insuffiecient

What Was Learned

Create a memo, summarizing declaration information and similar.

What Actions Are Required

Create memo and send to storekeeper, waste contractor and slop&cuttings contractor.