Lesson Learned





By: Stein-Petter Slatlem

Report No.

8202

Discipline/Origin

Drilling
No origin

Well

Kjøttkake
35/10-13

Date created

2025/02/02
307 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Cement
No classification

Deepsea Yantai


What happened in Surface section:
Hal Foam cementers had a check of line-up and inspected filter unit. Found a lot of Cement debris inside. Cleaned and cleared same.
They also observed Dry bulk hose on loading station without cap, making it possible to get moisture inside bulk hose.

What Was Planned

Debris in Cement Filter unit.

What Was Learned

Pre-checks are important.
There is also a ID change in CMT-line (from large to small) that might cause some CMT to stay in line after job, even after flushing.

What Actions Are Required

Go through routines for Cementer and deck. Verify no debris in filter unit and deck to install caps on bulk hoses.