What happened in Top hole:
Suction problems during start of cement job. Problems with suction due to air in mixing system. Resulting in erratic mixing densities. Had a 5-minute unplanned shut down while adding defoamer, before starting mixing again.

What Was Planned

Cement 30x 36” conductor to seabed with foam cement

What Was Learned

Start adding defoamer in first batch when starting mixing cement to establish stable parameters.
Consider pumping first cube without accelerator to have more time to react if mixing issues in the beginning of job happens again.

What Actions Are Required

HLB to follow up internally and consider implanting in procedures.