WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

8287

Discipline/Origin

Drilling
No origin

Well

Tomcat
6501/10-1

Date created

2025/02/15
294 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Reservoir section:
The overshot initially was not sent out with the Ardyne fishing basket. The overshot was planned out with the wrong connection. Ardyne informed they could supply the XO, but its difficult to M/U on the rig.

What Was Planned

To source the Ardyne side-door overshot as contingency to retrieve stuck wireline string.

What Was Learned

Evaluate to source the Archer side-door overshot in the future with correct connection and no need for XO. Or if Ardyne side-door overshot used – make up the XO onshore prior to shipment offshore.

What Actions Are Required

To consider for next operation.