WE Report

Lessons Learned

Lesson Learned





By: Lene Lomeland

Report No.

6967

Discipline/Origin

Drilling
No origin

Well

Falstaff
2/6-7 S

Date created

2024/11/11
390 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

What happened in P&A:
For plug #1D incorrect concentration of retarder was used in the cement mix – extending the thickening time substantially (from approximately 7 hrs to 36 hrs). When dressing off the cement – no hard cement was found until 2930 m (Cement plug #1D set from 3035-2814 m).

What Was Planned

Mix and pump cement according to cement program for P&A Plug #1.