Report No.

310

Discipline/Origin

Drilling
No origin

Well

Canela
6507/7-16 S

Date created

2019/01/07
2526 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Cement
Negative

Island Innovator


What happened in Surface section:
Not optimal cement recipe, needed 25 min to clean tanks between lead and tail slurry.

What Was Planned

Seawater-based mix water on lead cement and drill water based mix water on tail cement. Chemicals could not be mixed.

What Was Learned

Ensure cement recipes are compatible (lead/tail) to increase efficicency of job.

What Actions Are Required

Ensure cement recipes are compatible (lead/tail) to increase efficicency of job.