WE Report

Lessons Learned

Lesson Learned





By: Sander Schaathun

Report No.

5113

Discipline/Origin

Drilling
No origin

Well

Eirik (OMV)No well selected

Date created

2023/03/30
982 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Top hole:
Installation took about 0,5-0,75 hr rigtlme due to conductor movement and work above sea. Inclinometer measurements after the conductor was landed was not stable (or reliable), inclinatlno was flicking up and down between O and 2,4 degrees (while bullseye inclinations was reading properly around 0,7 deg inclination).

What Was Planned

Installation of LPWHH running tool in the moon pool.

What Was Learned

Run 2 x Bulls eye setup only, not recommended to run inclinometer.

Additional Documentation


LL-from-Eirik-OMV-1.pdf