WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5906

Discipline/Origin

No origin

Well

Norma
25/7-11 S

Date created

2023/09/03
825 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Positive

Deepsea Yantai


What happened in Reservoir section:
The primary MDT tool and BU failed. A additional MDT tool was mobilized from Deepsea Stavanger.

What Was Planned

As per plan one back-up MDT tool was mobilized for the Wireline operations at TD 8 1/2″ mainbore for data acquisition.

What Was Learned

To locate a new back-up tool if the primary fails, in case the BU also fails and a new tool needs to be mobilized on short notice.

What Actions Are Required

To locate a new back-up tool if the primary fails, in case the BU also fails and a new tool needs to be mobilized on short notice.