WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

232

Discipline/Origin

Logistics
No origin

Well

Grosbeak West
35/11-21 S

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Logistics
Negative

Transocean Arctic


What happened in Top hole:
Crane operator was unable to lift from supply vessel as basket was too heavy at one end due to 36″ bit placement.

What Was Planned

Perform heavy lift w/36″bit.

What Was Learned

Should attempt to balance basket with additional weight at opposite end to even out the weight distribution. Or ship 36″ bit, bit sub and string stabilizer as a more balanced sub-assembly.