What happened in Other:
An evaluation of some changes was not documented.
A MOC process should cover any RELEVANT changes to:
— surface and well control equipment;
— impact on WBEs;
— well type (e.g. conversion from producer to injector);
— procedures;
— rig or contractor well control equipment;
— key personnel;
— any change in design basis or operating condition for the well

What Was Planned

Changes related to documents and key personnel

What Was Learned

Evaluations of changes to organisation, documents and equipment that does not trigger a MoC process should be documented.

What Actions Are Required

Focus on Moc i bi-weekly /weekly meetings
Prepare a log where all MoC evaluations are documented