Report No.

395

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2095 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
A lot of extra work was promised orally to PGNiG.

What Was Planned

Expected deliveries

What Was Learned

Extra work, time consuming.

What Actions Are Required

Ensure it is very clear in contract what is included and what is not. Extra work to be agreed on an hourly rate.