WE Report

Lessons Learned

Lesson Learned





By: Drilling Supervisor

Report No.

2014

Discipline/Origin

Drilling
Experience Transfer Meeting

Well

Gomez
2/5-15

Date created

2021/08/14
1576 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Casing
Negative

Borgland Dolphin


What happened in Surface section:
The Franks split bushing spider (SBS) did not fit inside the EMSCO rotary table on Borgland Dolphin.

What Was Planned

Run 20″ casing using remote controlled spider type casing slips

What Was Learned

The SPS had been sent out with anti rotation lugs. These prevented the SBS to drop down into the rotary. The adapter ring had been back-loaded after the Oselvar project. It should have been kept onboard the rig.

What Actions Are Required

The lugs has to be removed from SBS onshore before shipped out. Alternatively the SBS with anti rotation lugs need an adapter ring it can sit on top of. This has to come out together with the SBS slips if it has rotation lugs.

What Was Done

The SBS was laid out, and we had to use the back-up the back-up vippe slips (also remote controlled. Lost 1.5 hr rig time.

External Actions

Get in contact with Franks coordinator in town?

What Was Done

The SBS was laid out, and we had to use the back-up the back-up vippe slips (also remote controlled. Lost 1.5 hr rig time.