WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

346

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2019/10/22
2237 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Nordkapp


What happened in Surface section:
IKM MRR: missing hoses between LARS and 90 degrees flowbend topside. Backloaded by Mi Swaco.

What Was Planned

Rig up MRR.

What Was Learned

Important that the equipment is checked ASAP on the rig to give the team time to mobilise new equipment
Cut return hose and used parts of same as contingency.

What Actions Are Required

MRR personnel should physically check their equipment in good time prior to operation.