Lesson Learned





By: Stein-Petter Slatlem

Report No.

8327

Discipline/Origin

Drilling
No origin

Well

Kjøttkake
35/10-13

Date created

2025/02/20
289 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Surface section:
Wrong lineup of hydraulic hoses from shore.

What Was Planned

Planned use of OWS FMS

What Was Learned

Correct lineup should be checked before equipment is shipped.

What Actions Are Required

Should be followed up onshore to make sure right lineup